Permit Information
Permit NumberFIR08-00778
StatusFinaled
Name CURTIS FIRE SPRINKLER SERVICE INC
Site Address 400 N BENJAMIN LN
Project NameBenjamin Campus
Customer NumberPHASE II
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding and relocating heads to accommodate new wall configurations in phase II.

Associated building permit BLD08-01664 (ADA COUNTY BENJAMIN CAMPUS - PHASE II) To remodel an existing 89,534 square foot warehouse/office building in phases. Phase I covered 41,700 square feet of the east side of the building and Phase II will cover the remaining 39,377 square feet of the west side of the building. Work to include: [installation of new non-bearing interior partition walls to create, five accessible restrooms on the first floor (ten stalls in the woman's, five stalls w/ four urinals in the mens room, and one unisex), two accessible restrooms on the second floor (two stalls in the woman's, one stall w/ one urinal in the men's and one unisex), open office area, 36 offices, a DMV lobby area (with 23 counter stations) five group rooms, a large meeting room, employee lounge, and other miscellaneous rooms and spaces], new lighting, new plumbing, new doors in specified locations, installation of suspended ceiling system, installation of new mechanical system (grilles, diffusers, ductwork, and new units), miscellaneous related interior finishes, demo of existing metal lean to at the back of the building and accessible parking w/curb cuts at the front of the building. This building is fully fire sprinklered any alterations to the sprinkler system shall be maintained per NFPA #13 as regulated by the fire department. The design, testing and utilization of industrial steel storage racks shall be in accordance with the RMI Specification for the Design, Testing and Utilization of Industrial Steel Storage Racks. A separate permit is required if any racks over eight feet are installed. This phase will be given a Temporary Certificate of Occupancy until phase I is completed then a Certificate of Occupancy will be issued to the entire building.**TLW**

System Design History
The original fire sprinklers system was reported designed for .33/3000 Extra Hazard with heads spaced at 80SF.

The alterations will be based on .10/1114 SF. Light Hazard with SSP up to 225 SF and EC up to 400SF. The quick response modifier has been applied to the hydraulic calculations.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/30/20093/31/20093/31/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection3/30/20093/30/20093/30/2009PFAIL
DetailsTroy Cobbley
No testing could be completed today due to multiple problems with the pressure switches.
INSP-Sprinkler Rough-in/Hydro3/25/20093/26/20093/26/2009APASS
DetailsTroy Cobbley
All items have been corrected except the interconnection/operation of the pre-action system.
INSP-Sprinkler Rough-in/Hydro3/25/20093/25/20093/25/2009APART
DetailsTroy Cobbley
There are four deficiencies prior to final sign off. The heads at the top and bottom of the elevator shaft are not oriented correctly. The sprinkler piping to the head at the bottom of the shaft is not secured and needs a cage. One head on the second floor is bent and needs replaced and one upright sprinkler head in a warehouse storage room is blocked by a pendant light. Also the pre-action system has not been tested. The other deficiencies have been corrected and marked off on the city approved plans.
INSP-Sprinkler Rough-in/Hydro3/13/20093/13/20093/13/2009PPASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping can be covered.
INSP-Sprinkler Rough-in/Hydro2/23/20092/23/20092/23/2009AFAIL
DetailsTroy Cobbley
The insulation had not been addressed on the second floor mezzanine so the inspection was stopped until all items are addressed. Per the contractor other areas will be ready at the next inspection.
INSP-Sprinkler Rough-in/Hydro2/20/20092/20/20092/20/2009PPART
DetailsTroy Cobbley
See the city approved plans for locations on the second floor where corrections are needed.
INSP-Sprinkler Rough-in/Hydro2/3/20092/4/20092/4/2009ADONE
DetailsTroy Cobbley
This inspection was actually a conference to see where combustibles above the ceiling had been covered with drywall and areas that had not been covered yet.
INSP-Sprinkler Rough-in/Hydro1/12/20091/12/20091/12/2009PPASS
DetailsTroy Cobbley
The rough-in for the pre-action system passed. the hydro test passed.
INSP-Conference12/18/200812/18/200812/18/2008PDONE
DetailsTroy Cobbley
I deferred the sprinkler design questions to tim frost. This is a fully sprinklered building but there is exposed wood in the above ceiling area.