Description |
The Fire Sprinkler Scope of work consists of adding and relocating heads to accommodate new wall configurations in phase II.
Associated building permit BLD08-01664 (ADA COUNTY BENJAMIN CAMPUS - PHASE II) To remodel an existing 89,534 square foot warehouse/office building in phases. Phase I covered 41,700 square feet of the east side of the building and Phase II will cover the remaining 39,377 square feet of the west side of the building. Work to include: [installation of new non-bearing interior partition walls to create, five accessible restrooms on the first floor (ten stalls in the woman's, five stalls w/ four urinals in the mens room, and one unisex), two accessible restrooms on the second floor (two stalls in the woman's, one stall w/ one urinal in the men's and one unisex), open office area, 36 offices, a DMV lobby area (with 23 counter stations) five group rooms, a large meeting room, employee lounge, and other miscellaneous rooms and spaces], new lighting, new plumbing, new doors in specified locations, installation of suspended ceiling system, installation of new mechanical system (grilles, diffusers, ductwork, and new units), miscellaneous related interior finishes, demo of existing metal lean to at the back of the building and accessible parking w/curb cuts at the front of the building. This building is fully fire sprinklered any alterations to the sprinkler system shall be maintained per NFPA #13 as regulated by the fire department. The design, testing and utilization of industrial steel storage racks shall be in accordance with the RMI Specification for the Design, Testing and Utilization of Industrial Steel Storage Racks. A separate permit is required if any racks over eight feet are installed. This phase will be given a Temporary Certificate of Occupancy until phase I is completed then a Certificate of Occupancy will be issued to the entire building.**TLW**
System Design History
The original fire sprinklers system was reported designed for .33/3000 Extra Hazard with heads spaced at 80SF.
The alterations will be based on .10/1114 SF. Light Hazard with SSP up to 225 SF and EC up to 400SF. The quick response modifier has been applied to the hydraulic calculations.
|