Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR08-00786
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 5600 E WARM SPRINGS AVE
Project NameEAST JR HIGH SCHOOL
Customer Number 
ePlanReview 
Description
NOTE TO INSPECTOR: The notification devices with guards are to have wire guards only for this permit. Plastic or Lexan guards for the notification devices are not allowed under this permit.

This fire alarm permit is to provide a new manual fire alarm system in a new building. Permit scope to include pull stations, full area smoke detection, full notification, sprinkler system monitoring, HVAC monitoring, and elevator recall functions.

Associated building permit: BLD07-01910 East Junior High - To construct a new 120,805 square foot, two story, masonry and steel framed junior high school and related site improvements. This building is separated by two hour fire walls into three separate buildings. Section One is Type II One-hour construction and contains the gymnasiums, locker rooms, kitchen and cafeteria and administrative offices on the first floor and library and computer/technology areas on the second floor. The first floor is 50,415 sq. ft. and the second floor is 10,150 sq. ft.. Section Two is Type II nonrated construction and contains classrooms on the first and second floors. First floor 15,275 sq. ft. and second floor 14,450 square feet. Section Three is Type II nonrated construction and contains classrooms on the first and second floors. First floor 15,145 sq. ft. and second floor 15,370 square feet. This building is fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/22/20096/22/20096/22/2009APASS
DetailsForrest France
Record drawings accepted, fire alarm permit okayed for final status.
INSP-Final Inspection6/15/20096/15/20096/15/2009ADONE
DetailsForrest France
Contact Mark Phone#: ###-####
INSP-Alarm Testing6/1/20096/1/20096/2/2009APART
DetailsForrest France
See stamped plan set for areas inspected to date.
INSP-Alarm Testing5/26/20095/29/20095/29/2009APART
DetailsForrest France
Completed fire alarm testing for the second floor classroom wings areas F and G. Noted three smoke detectors to be moved due to overspacing, one notification appliance is overspaced, also annotated field changes including deleted dampers, door holds and smoke detectors at some areas.
INSP-Alarm Testing5/26/20095/28/20095/28/2009APART
DetailsForrest France
Fire alarm testing completed for the second floor media center areas and adjacent corridors areas F and G, need access to test devices in one locked storage room, one SD to be added at the circulation desk, noted deleted points including door holders, dampers, relocated nac panel and deleted sd to be included on as-built set. Non-functional damper at the electrical room 1st floor retested okay after repair.
INSP-Alarm Testing5/26/20095/27/20095/27/2009APART
DetailsForrest France
Completed fire alarm testing for areas D and E first floor including the elevator-see plans for annotations. Noted one fire damper at the electrical room adjacent to the riser room which did not operate, retest for items noted yesterday okayed, as-builts for deleted points to be reflected on record drawings.
INSP-Alarm Testing5/25/20095/26/20095/26/2009APART
DetailsForrest France
Completed fire alarm testing for areas A, B, and C today. Noted on plans one smoke detector to be relocated, need to repair non-functional dampers at the cafeteria, deleted devices at the electrial room, kitchen and dampers at various locations must be indicated on record drawings. See plans for annotations.
INSP-Alarm Testing5/20/20095/20/20095/20/2009PCANC
DetailsTroy Cobbley
To be rescheduled due to being overbooked.
INSP-Alarm Testing5/18/20095/19/20095/19/2009PCANC
DetailsTroy Cobbley
Cancelled per conversation with Mark.
INSP-Conference5/18/20095/18/20095/18/2009PDONE
DetailsForrest France
Scheduled by a contractor via Hello! on 5/18/2009 at 9:12:04 AM. Contact: ###-####.
INSP-Alarm Testing5/13/20095/14/20095/15/2009APART
DetailsForrest France
See permit activity comments for work completed to date.
INSP-Alarm Testing5/13/20095/15/20095/15/2009APART
DetailsForrest France
Testing completed for fire alarm notificaiton, initiation, and duct smoke detection for area "A" as marked on plan set. Still need record of inspection and testing forms and original stamped plan set, need to verify dB readings do not exceed max. allowed at the locker room and mechanical room entrys, provide correct descriptors matching sprinkler riser zones, verified account is set up, noted phone line troubles are not annunciated at the FACP-only indicated at the security panel.
INSP-Alarm Testing5/12/20095/13/20095/13/2009AFAIL
DetailsTroy Cobbley
The original city approved plans were not provided. All of the signals sent to the monitoring company were undefined even though I had been told that the monitoring had been set up. The phone line #2 did not report a trouble signal when disconnected. Labels need to be provided at the NAC panels and the fire sprinkler risers. See the onsite plans for devices tested on the first floor administrative area. These will need to be retested due to the signals not being sent. Also see this set of plans for room descriptions that smoke detectors had that did not match those on the plans. The NAC panels interconnection with the facp was verified for supervision. Both phone lines have separate phone numbers as well.
INSP-Alarm Testing5/7/20095/8/20095/8/2009ANR
DetailsForrest France
Scheduled by a contractor via Hello! on 5/7/2009 at 4:35:36 PM. Contact: ###-####. Discussed items for final and project schedule.
FIR-Aging Inspection3/9/20093/9/20093/9/2009 DONE
DetailsForrest France
Site visit confirmed construction underway, work in progress.