Permit Information
Permit NumberFIR09-00027
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 234 S WHISPERWOOD
Project NameMEP GROUP LLC
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of 165'x6" underground ONLY. The above system will follow at a later date under a separate permit.

The MEP Group Office Shell - To construct a new 11,580 square foot, one story with a 1,445 square foot mezzanine, wood framed office shell building and related site improvements. This building is designed for two future office tenant spaces. This is a shell permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building will be fully fire sprinkled. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Sprinkler Rough-in/Hydro5/19/20095/20/20095/20/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/19/20095/20/20095/20/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection5/14/20095/15/20095/15/2009APART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro4/14/20094/15/20094/15/2009APASS
DetailsTroy Cobbley
The underground hydro test passed
INSP-Sprinkler Rough-in3/23/20093/23/20093/23/2009PPASS
DetailsTroy Cobbley
The thrust block at the 45 has been replaced and the remaining underground piping can be covered.
INSP-Sprinkler Rough-in3/18/20093/19/20093/23/2009PPASS
DetailsTroy Cobbley
The thrust block at the 45 has been replaced and the remaining underground piping can be covered.
INSP-Sprinkler Rough-in/Hydro3/19/20093/20/20093/20/2009AFAIL
DetailsForrest France
Thrust block at the 45 deg ell is not satisfactory, noted one section of piping needs properly bedded, remiander of installation is okay for cover-see plans for locations approved for bury.
INSP-Final Inspection2/26/20092/27/20092/26/2009PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 2/26/2009 at 2:54:20 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 26 2009 2:56PM.
INSP-Sprinkler Rough-in1/23/20091/23/20091/23/2009PPASS
DetailsTroy Cobbley
The in building riser and 5'-0" stub out are ok to bury