INSP-Final Inspection | 5/11/2009 | 5/12/2009 | 5/12/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 5/8/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The scope of work has been modified as requested.
|
INSP-Alarm Testing | 5/6/2009 | 5/7/2009 | 5/7/2009 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Darren.
|
INSP-Alarm Testing | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | PART |
Troy Cobbley
|
|
|
The notification devices operated in the six new office/meeting rooms. Plan resubmittals are required due to another area to the south, sheet 5 of 5, where work has not been performed. Per the personell on site this work is not going to be performed which changes the scope of work for the fire alarm permit thus the reason for the resubmittal. The other reason is instead of 15cd strobes being installed in the six rooms 30cd strobes have been installed which changes the battery and EOL calculations.
|
INSP-Alarm Testing | 3/30/2009 | 3/31/2009 | 3/31/2009 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 3/30/2009 at 3:21:50 PM. Contact: ###-####.
|