Permit Information
Permit NumberFIR09-00082
StatusFinaled
Name ALARMCO
Site Address 12000 W EXECUTIVE DR
Project NameEXECUTIVE BUILDING
Customer Number 
ePlanReview 
Description
12/23/10 PLAN MODFICIATION #2 (4 Initiating devices affected): This plan modification is to relocate the existing pull station, show the existing duct detectors and their locations (not indicated on previous submittals), and provide corrected zone configurations.

11/29/10 PLAN MODIFICATION (10 Initiating devices affected): This plan modification is to include connections to a new fire pump, modify the location of the AES, and to relocate the existing fire alarm panel. An IntelliTap is being provided with this AES panel.

2/9/09:
This fire alarm permit is to replace the DACT (phone lines) functions with RF Radio for monitoring. There is no associated building permit.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/17/20112/17/20112/17/2011PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection2/15/20112/15/20112/15/2011PFAIL
DetailsTroy Cobbley
The tamper switches tested ok but came in on the same zone the the map indicated that the duct smoke detectors were on. So we tested two of the four duct smoke detectors and found that they havent been connected to the FACP. The duct detectors need to be connected to the FACP and the map corrected.
INSP-Final Inspection2/14/20112/15/20112/15/2011ACANC
DetailsTroy Cobbley
I called Bryan at ###-#### twice before going to the project and once after I arrived at the project but did not contact him. I left messages. No inspection was performed.
INSP-Final Inspection2/4/20112/7/20112/7/2011AFAIL
DetailsTroy Cobbley
Three tamper switches need to be adjusted. This includes two in the valve pit and one on the jockey pump.
INSP-Final Inspection2/2/20112/3/20112/3/2011PCANC
DetailsTroy Cobbley
Cancelled due to time constraints with micron plan review and inspection work load. Also per Guy, the fire sprinkler contractor needed to get setup for the phase reversal and loss of power signals. Will probably be rescheduled for next week.
INSP-Final Inspection11/15/201011/15/201011/15/2010PFAIL
DetailsTroy Cobbley
After arriving on site it was determined that this permit will be postponed due to a plan modification being performed to include additional fire alarm work.
FIR-Aging Inspection10/27/201010/27/201010/28/2010 NR
DetailsTroy Cobbley
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
FIR-Aging Inspection6/22/20106/22/20106/22/2010 FAIL
DetailsForrest France
See inspection activity 1/26/10.
INSP-Final Inspection1/25/20101/26/20101/26/2010AFAIL
DetailsForrest France
Need to provide verification that tamper switches at the pit backflow shutoff valves #1 and 2 are connected to the panel- as FLP wire is disconnected and exposed at a junction box labeled "pit valve os&y" in the riser room. Also need to retest alarm signals as the manual pull station failed to report.
INSP-Final Inspection12/8/200912/9/200912/9/2009PCANC
DetailsTroy Cobbley
Cancelled per Guy. To be rescheduled.
FIR-Aging Inspection6/23/20096/23/20096/23/2009 NR
DetailsTroy Cobbley
work is in progress