INSP-Final Inspection | 2/7/2011 | 2/8/2011 | 2/8/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/2/2011 | 2/3/2011 | 2/3/2011 | P | FAIL |
Troy Cobbley
|
|
|
All signals are ok except the trouble signals are not being sent out from the AES but restore signals are being sent out on the intella tap. It appears the wiring between the AES and the FACP may be suspect.
|
INSP-Final Inspection | 2/1/2011 | 2/2/2011 | 2/2/2011 | P | CANC |
Troy Cobbley
|
|
|
Please call Guy at ###-#### with inspection time. Phone #: ###-#### >> Inspection requested via web by Lori Brungardt Inspection cancelled from web by: Lori Brungardt
|
INSP-Final Inspection | 1/31/2011 | 2/1/2011 | 2/1/2011 | P | FAIL |
Troy Cobbley
|
|
|
The flow switch signal made it to the monitoring station but did not show up on Guys computer. The tamper switch is out of adjustment. After we left the building and started another inspection across the parking lot supervisory signals were coming in from this job. Basically this inspection will need to be redone.
|
FIR-Aging Inspection | 10/28/2010 | 10/28/2010 | 10/28/2010 | | NR |
Troy Cobbley
|
|
|
Work is in progress. Per Guy all of these AES inspections are being called in shortly.
|
FIR-Aging Inspection | 7/7/2010 | 7/7/2010 | 7/7/2010 | | NR |
Troy Cobbley
|
|
|
Per Bill the AES inspection scheduling is being addressed.
|
FIR-Aging Inspection | 5/21/2009 | 5/21/2009 | 5/21/2009 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|