INSP-Final Inspection | 10/20/2009 | 10/20/2009 | 10/20/2009 | P | PASS |
Troy Cobbley
|
|
|
The syncing of the handicap rooms a/v's has been addressed. The placement and testing of the atrium smoke detectors has been addressed. Permit finaled.
|
INSP-Alarm Testing | 10/9/2009 | 10/9/2009 | 10/9/2009 | A | PASS |
Troy Cobbley
|
|
|
The sync issue between the common area a/v's and the handi-cap room a/v's has been resolved and tested ok. Waiting on the resubmittals showing this work and the resolution with the atrium.
|
INSP-Alarm Testing | 10/1/2009 | 10/1/2009 | 10/1/2009 | P | PASS |
Troy Cobbley
|
|
|
All of the smoke alarms were tested today as well as all of the fire sprinkler to fire alarm panel interconnections. There are two items left that need addressed. They are the shutters on the third floor atrium and the non-syncing of the horn/strobes in the first floor common areas and the handi-cap rooms.
|
INSP-Final Inspection | 9/29/2009 | 9/30/2009 | 9/30/2009 | A | FAIL |
Troy Cobbley
|
|
|
The smoke duct detectors for hvac shutdown and the fire/smoke dampers passed inspection today. Also the hood suppression system interconnection passed inspection. The 14ga wire has been installed at the NAC panels as well.
|
INSP-Final Inspection | 9/28/2009 | 9/29/2009 | 9/29/2009 | A | FAIL |
Troy Cobbley
|
|
|
The inspection continued today. Items left to test include the hood suppression system, hvac shutdown, EOL voltage drop, smoke alarms, smoke shutters/atrium smoke detectors and sprinkler system interconnections. Notification and initiating (smoke detectors/pull stations) were tested on all floors. Two were repaired while I waited.
|
INSP-Final Inspection | 9/25/2009 | 9/28/2009 | 9/28/2009 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the initiating devices tested today as marked in red. The phone lines and supervision of the NAC panels were verified. One 16ga wire needs to be changed to 14ga as discussed and atrium smoke shutter sequence of operation needs to be verified since it has not been programmed per the approved drawings.
|
INSP-Alarm Testing | 7/6/2009 | 7/7/2009 | 7/7/2009 | A | PASS |
Troy Cobbley
|
|
|
The rough-in inspection for the riser room is passed.
|
INSP-Alarm Testing | 7/1/2009 | 7/1/2009 | 7/1/2009 | P | PASS |
Troy Cobbley
|
|
|
The fire alarm rough-in for the first floor passed.
|
INSP-Alarm Testing | 6/24/2009 | 6/24/2009 | 6/24/2009 | P | PASS |
Troy Cobbley
|
|
|
The fire alarm rough-in for the second floor passed. One smoke detector appears to be overspaced from the east fire doors and will be verified at the final.
|
INSP-Alarm Testing | 6/9/2009 | 6/9/2009 | 6/10/2009 | P | DONE |
Troy Cobbley
|
|
|
This was a rough-in inspection for the center building third floor fire alarm system which passed.
|
INSP-Alarm Testing | 4/8/2009 | 4/8/2009 | 4/9/2009 | P | CANC |
Troy Cobbley
|
|
|
The wrong inspection number was called in.
|
INSP-Sprinkler Rough-in | 4/6/2009 | 4/6/2009 | 4/7/2009 | P | CANC |
Troy Cobbley
|
|
|
wrong permit called in.
|