The Fire Sprinkler Scope of work consists of dropping sprinklers below a new ceiling with arm overs.

(ECCO) Remodel to a portion of the existing 40,335 square foot first floor and a first time tenant improvement to the 9,230 square foot second floor. NOTE: This building is fully fire sprinklered for area increase. Work to the first floor to include: Adding new elevator, elevator equipment room constructed of 8" concrete smooth surface block on the exterior of the building , new Concore 2500 Access floor panel system in the server room, extending the existing server room walls to the underside of the second floor, construction of new walls for a lab area with a new door/tempered window, construction of new walls for a break room, and other misc. work per the plans. Work to the second floor to include: Construction of new walls for a new conference room, offices, mail room, smaller conference room, corridor with a breakroom/coffee station, one men's restroom, one women's restroom, one unisex restroom, and second floor framing construction for new HVAC and janitor/storage rooms. Second floor misc. work to include: New glass handrail, relocating a ducting chase, modifying the vestibule ceiling, slopeing gypcrete flooring down to plywood floor landings at both stairs, and adding office cubicels. All work per approved plans, Engineering, attached Plan review report, and CZC08-00167. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/6/20095/7/20095/7/2009APASS
DetailsForrest France
Corrections verified for completion, fire sprinkler permit finaled.
INSP-Final Inspection5/6/20095/6/20095/6/2009AFAIL
DetailsForrest France
Mixed response heads at the 2nd level ceiling above the front entry area need to match remainder of quick response heads provided at the remodel area.
INSP-Sprinkler Rough-in/Hydro4/9/20094/10/20094/10/2009APART
DetailsForrest France
Need resubmitted plans for modifications at the new lunchroom, mech. room, and elevator pit, noted one missing retaining strap. Missing hanger per previous inspection installed.
INSP-Supply line flush3/9/20093/10/20093/10/2009APASS
DetailsTroy Cobbley
This inspection was not for a flush but actually a cover inspection for the remaining sprinkler piping on the second floor. THe piping is ok to cover. Work is not complete in the mechanical room or in the elevator shaft which is not shown on this seto of sprinkler plans.
INSP-Sprinkler Rough-in2/10/20092/11/20092/11/2009APART
DetailsTroy Cobbley