INSP-Final Inspection | 3/31/2010 | 4/1/2010 | 4/1/2010 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/26/2009 | 3/27/2009 | 3/27/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/25/2009 | 3/26/2009 | 3/26/2009 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for a final due to dry system hydro test failure.
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2009 | 3/26/2009 | 3/26/2009 | A | PART |
Troy Cobbley
|
|
|
The sprinkler head change out passed. The hydro test for the wet system passed. The hydro test for the dry system failed due to a leaking 4" main.
|
INSP-Conference | 3/25/2009 | 3/25/2009 | 3/25/2009 | P | PASS |
Troy Cobbley
|
|
|
I confirmed with Larren that I would only require a hydro test on the replaced/recalled sprinkler heads as per NFPA 25. I would consider the three non-recall dry pendants a maintenance issue which they could replace at their leisure without being included with the hydro testing.
|