INSP-Final Inspection | 2/24/2011 | 2/24/2011 | 2/24/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/23/2011 | 2/23/2011 | 2/23/2011 | P | FAIL |
Troy Cobbley
|
|
|
The approved plans are missing so no actual inspection was performed. The netcon was now a 5.
|
INSP-Final Inspection | 2/18/2011 | 2/22/2011 | 2/23/2011 | A | DEFR |
Forrest France
|
|
|
Scheduled 2/23 PM.
|
INSP-Final Inspection | 2/17/2011 | 2/17/2011 | 2/17/2011 | P | FAIL |
Troy Cobbley
|
|
|
Cancelled due to time constraits.
|
FIR-Aging Inspection | 2/9/2011 | 2/9/2011 | 2/10/2011 | | NR |
Troy Cobbley
|
|
|
Per Bill these inspections are being addressed.
|
FIR-Aging Inspection | 11/16/2010 | 11/16/2010 | 11/16/2010 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
INSP-Sprinkler Rough-in/Hydro | 4/1/2010 | 4/2/2010 | 4/2/2010 | P | FAIL |
Troy Cobbley
|
|
|
We verified the Netcon rating at the beginning of the inspection and found that it got only a 6. U.L. listing is for a 5 or less. No other items inspected.
|