INSP-Final Inspection | 7/20/2009 | 7/23/2009 | 7/23/2009 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work okayed for final status.
|
INSP-Sprinkler Rough-in | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | PART |
Forrest France
|
|
|
Need access to the west half of the attic space for tenting and insulation inspection.
|
INSP-Conference | 6/16/2009 | 6/16/2009 | 6/16/2009 | P | DONE |
Forrest France
|
|
|
Regarding outside waterflow bell and existing fire alarm panel.
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2009 | 6/15/2009 | 6/15/2009 | P | PART |
Forrest France
|
|
|
Pending completion of tenting for cold cavity protection of wet system piping.
|
INSP-Supply line flush | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PART |
Forrest France
|
|
|
UG fire supply line flush witnessed acceptable.
|
INSP-Supply line flush | 5/21/2009 | 5/27/2009 | 5/27/2009 | P | FAIL |
Forrest France
|
|
|
No water available for the underground flush, preliminary walkthrough for the overhead installation done, riser is not finished at this time.
|
INSP-Sprinkler Rough-in | 5/19/2009 | 5/20/2009 | 5/20/2009 | A | PART |
Troy Cobbley
|
|
|
The underground piping installed is 1 1/4" cpvc. Per the approved plans, note #4, if the piping is not poly then resubmittals are required. I contacted bruce about this but gave him the ok to cover. It also appears that the underground supply is coming up closer to the exterior wall than what is shown on the plans. This too will need to be addressed.
|