INSP-Final Inspection | 6/29/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flush passed.
|
INSP-Final Inspection | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler piping in the wash bay has been modified to match original approved plan. Forward flush failed.
|
INSP-Final Inspection | 6/23/2009 | 6/23/2009 | 6/23/2009 | P | FAIL |
Troy Cobbley
|
|
|
The plans do not reflect the additional sprinklers heads in the compressor room that have been added to the the anti-freeze system. Per my discussion with Tim Frost these changes need to be resubmitted due to the adjacent remote hydraulic area being effected by a non self closing door. Also two 45 fittings have been added at the base of the riser which are not shown on the plans. The backflow preventor needs to be certified and the forward flush performed.
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2009 | 6/15/2009 | 6/16/2009 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed. The FDC piping was not included in the hydro test and will need to be done.
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2009 | 6/10/2009 | 6/10/2009 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was a rough-in. See the city approved plans for the corrections required which include an overspaced head, a pendant that needs to be supplied from its own mechanical tee, additional hangers on the 2" anti-freeze supply piping and resubmittals showing the anti-freeze system in the front entry canopy and the modifications at the wash bay.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2009 | 5/6/2009 | 5/7/2009 | P | PART |
Troy Cobbley
|
|
|
The sprinkler piping above the office/lobby/storage areas are ok to cover
|
INSP-Sprinkler Rough-in | 5/4/2009 | 5/4/2009 | 5/4/2009 | P | PART |
Troy Cobbley
|
|
|
The rough-in inspection for the piping below the mezzanine passed. An additional inspection will be required when the ceilings and light fixtures have been installed.
|