INSP-Final Inspection | 12/31/2009 | 12/31/2009 | 12/31/2009 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PART |
Forrest France
|
|
|
Correction notice items completed, final pending satisfactory alarm permit final for system supervision.
|
INSP-Final Inspection | 12/15/2009 | 12/16/2009 | 12/16/2009 | A | NR |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: Scott Carter II
|
INSP-Final Inspection | 12/11/2009 | 12/15/2009 | 12/15/2009 | A | NR |
Forrest France
|
|
|
Noted one SW head at the first floor mechanical closet in need of adjustment, provide "911" sign at the outside bell, project related FIR permits 09-00283 thru 286 are "ready to issue", need escutcheons installed and travel caps removed at units 518,520, and 524, noted heat has been provided and sheetrock ceilings in the shell unit are done, riser supervision to be tested in conjunction with fire alarm permit work re-inspect.
|
INSP-Sprinkler Rough-in/Hydro | 10/15/2009 | 10/16/2009 | 10/16/2009 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed. This is just a preliminary hydro since not all of the sprinkler system has been installed.
|
INSP-Sprinkler Rough-in/Hydro | 10/14/2009 | 10/15/2009 | 10/15/2009 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cove in units 105 and 205. Resubmittal are needed since the pipe sizing and routing have changed and feeds the remote area. I have marked the "as installed" size and routing on the city approved plans. I let the sprinkler fitter know that If ceilings and piping need to be removed due to the resubmittal plans that is the burden of the contractor.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2009 | 10/14/2009 | 10/14/2009 | A | CANC |
Troy Cobbley
|
|
|
Overbooked. I spoke to the contact to have them reschedule for tomorrow.
|
INSP-Sprinkler Rough-in | 7/27/2009 | 7/27/2009 | 7/27/2009 | P | PART |
Forrest France
|
|
|
Approved overhead cover for unit 101 and 201east side 516.
|
INSP-Sprinkler Rough-in | 5/19/2009 | 5/19/2009 | 5/19/2009 | P | PASS |
Troy Cobbley
|
|
|
The 2" underground supply piping is ok to cover. The contractor did not have the original approved plans, just copies, on site. I let him know those would be needed at the next inspection.
|