Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR09-00316
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 1352 S EAGLE FLIGHT WAY
Project NamePintail Center - Blackeagle
Customer Number 
ePlanReview 
Description
This fire alarm permit is to replace the existing fire alarm system with new due to a remodel. System includes smoke detectors (voluntarily above panels), pull stations, HVAC shutdown/monitoring, sprinkler system monitoring, and full notification.

Associated building permit: BLD09-00537 (COLLEGE OF WESTERN IDAHO) To remodel the interior of a 52,295 sq. ft. building for use as Adult Education facility. The building is fully sprinklered W/ 60' yards all around for unlimited area. Interior demolition under way - BLD09-00350. To construct new interior walls to create nonrated corridor and accessible route to all portions of the building; new partitions creating multiple computer labs, classrooms, administrative staff offices, students common area, upgrading and maintaining accessible restroom facilities and current exit paths and egress doors serving the existing interior court, new suspended ceiling grid system, upgrade of electrical, plumbing, mechanical, sprinkler and alarm systems and interior cabinetry and finishes, all per reviewed plans. There is no structural work being performed as part of this permit. Drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/27/20097/27/20097/27/2009PPASS
DetailsForrest France
Notification in areas A and C passed field testing, mag locks at one location tied in and tested while on site, fire alarm permit finaled.
INSP-Final Inspection7/23/20097/24/20097/24/2009ADEFR
DetailsForrest France
Randy or Kelly ###-#### Phone #: ###-####
INSP-Alarm Testing7/15/20097/16/20097/16/2009ADONE
DetailsTroy Cobbley
Fire alarm system is complete in areas 'B' and 'D'. Un-needed sample tubes from the duct detectors have been removed. However, there are 41 HVAC units with duct detectors but only 39 sample tubes are accounted for. The two missing additional sample tubes will need to be provided prior to final.
INSP-Alarm Testing7/13/20097/14/20097/14/2009AFAIL
DetailsTroy Cobbley
Todays inspection was for areas B and D. Alarms will be complete in these two areas when Alarmco finals their AES system and the samples tubes are installed correctly in the existing duct smoke detectors or verification is provided that this was an exceptable installation at the time the building was built.
INSP-Alarm Testing7/13/20097/13/20097/13/2009PPART
DetailsTroy Cobbley
The fire alarm panel and the interconnection with the NAC in the east end were tested today. The AES system installed by Alarmco was not tested. They were contacted about the importance of getting this inspected right away. The notification devices in areas B and D were tested. The strobe and horns functioned but the WP horn/strobe in the east end of the central garden did not function. Also several strobes are overspaced, see plans, and two additional strobes have been added in the east corridor as marked on the approved plans. No duct smoke detectors have been tested at this time.
INSP-Alarm Testing7/9/20097/10/20097/10/2009AFAIL
DetailsTroy Cobbley
Per the installer, who was not at the project site, the fire alarm system is not ready to test due to an issue with a duct smoke detector. No inspection was performed.