INSP-Final Inspection | 12/28/2009 | 12/29/2009 | 12/29/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit final approved.
|
INSP-Final Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection.
|
INSP-Final Inspection | 12/21/2009 | 12/22/2009 | 12/22/2009 | P | NR |
Forrest France
|
|
|
Painted heads need replaced, riser supervision is incomplete.
|
INSP-Sprinkler Rough-in/Hydro | 12/21/2009 | 12/22/2009 | 12/22/2009 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic retest passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2009 | 12/18/2009 | 12/21/2009 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to pressue loss at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2009 | 12/17/2009 | 12/17/2009 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic testing failed due to pressure loss at the guage and visible leakage at two locations.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2009 | 12/16/2009 | 12/16/2009 | A | NR |
Forrest France
|
|
|
Hydro - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley NOTE: Not ready for inspection per contractor- to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2009 | 12/17/2009 | 12/16/2009 | A | CANC |
Forrest France
|
|
|
Final - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 12/14/2009 | 12/15/2009 | 12/15/2009 | P | FAIL |
Forrest France
|
|
|
Inspection for overhead cover at the drop ceilings in the corridors and adjacent rooms failed due to some items including missing seismic bracing, one blocked upright, two areas missing coverage, one mixed head, one upright to be relocated- see plans for red-lines.
|
INSP-Sprinkler Rough-in | 10/23/2009 | 10/23/2009 | 10/23/2009 | P | PART |
Forrest France
|
|
|
Todd Phone#: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2009 | 10/21/2009 | 10/21/2009 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work at the sheetrock ceiling above the reception desk is okay for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/13/2009 | 10/14/2009 | 10/14/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas marked in red with todays date where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in | 10/5/2009 | 10/5/2009 | 10/5/2009 | P | PART |
Forrest France
|
|
|
Okayed for cover as marked on approved plan set.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2009 | 9/18/2009 | 9/18/2009 | A | PART |
Forrest France
|
|
|
Inspection for overhead cover okayed for the boy's restroom only, HVAC ducting at the girls restroom side obstructs coverage at one upright.
|