INSP-Final Inspection | 12/23/2009 | 12/24/2009 | 12/24/2009 | A | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2009 | 10/26/2009 | 10/26/2009 | A | PART |
Forrest France
|
|
|
Final pending grid ceilings, tile and escutcheons.
|
INSP-Sprinkler Rough-in | 10/21/2009 | 10/21/2009 | 10/21/2009 | P | PART |
Forrest France
|
|
|
Added pendent in the concealed combustible space at the second level is approved for cover, remainder of items on C/N are not yet finished.
|
INSP-Sprinkler Rough-in/Hydro | 10/15/2009 | 10/15/2009 | 10/15/2009 | P | PART |
Troy Cobbley
|
|
|
See the city approved quick permit plans for specific areas that are ok to cover such as the stairs and a small soffit. The ceiling t grid neds installed so that pendant placement can be verified. Also on the second floor mechanical room an existing pendant head is now blocked by a new plumbing pipe and also on the second floor a wall has been built that forms a combustible concealed space that will require protection.
|