Permit Information
Permit NumberFIR09-00612
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2786 E HARD ROCK DR
Project Name2786 E HARD ROCK DR
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of fire protection for a new home. There is one level with a finished basement. The system has been designed per NFPA 13D. There is a 1 ½" underground supply through a meter and backflow preventer. Sprinklers have been designed for a 18'x18'' spacing.

Permit for the construction of a new 6589 sq. ft. one story single family dwelling with a basement wth the basement being 2147 sq. ft. with one bedroom and one bathroom and the first story consisting of 5 bedrooms and 3 1/2 bathrooms. All work to be done per the approve plans, plan review report, attached engineering and any notations. Fire sprinklers are required in this dwelling. A letter from the applicant's geotechnical engineer indicating that the footing sub-grade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at 384-3946. Prior to obtaining a final for the permit, the roof drainage system must be inspected by Boise Public Works. Call Terry Records at 384-3946. R-1A 1DA zoning, CFH09-15 and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/6/20105/7/20105/7/2010PPASS
DetailsForrest France
Corrections field verified, fire sprinkler permit final approved.
INSP-Final Inspection5/4/20105/5/20105/5/2010PFAIL
DetailsForrest France
Two pendent heads at the first floor living room are blocked by surface mounted ceiling obstructions, missing escutcheon at one sw head basement level, master bedroom 2nd pc. canopies need adjustment, delay at flow switch <5 sec.
INSP-Final Inspection4/1/20104/1/20104/1/2010PPART
DetailsForrest France
Construction underway
INSP-Supply line flush1/27/20101/28/20102/1/2010PPART
DetailsForrest France
Supply line flush okayed per site visit and activity notes 1/29.
INSP-Supply line flush1/28/20101/29/20101/29/2010APART
DetailsForrest France
Supply line flush completed acceptable.
INSP-Final Inspection1/14/20101/15/20101/15/2010APART
DetailsForrest France
Remainder of overhead rough-in okayed for cover at both basement and first floor levels.
INSP-Sprinkler Rough-in1/13/20101/14/20101/14/2010APART
DetailsForrest France
Overhead rough-in is satisfactory except as noted on plans-one area missing drops is incomplete, main level bedroom #2 head appears too close to a ceiling fan as marked on drawings, riser not yet tied in, discussed supply line flush, tenting is acceptable.