Permit Information
Permit NumberFIR09-00642
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of various areas listed below:
- Receiving Area East & West - Ordinary Hazard Group II (Storage not to exceed 12' high, 130 sf see NFPA 13: 5-3.2)
- Dock - Ordinary Hazard Group II (Storage not to exceed 12' high, 130 sf see NFPA 13: 5-3.2)
- Dry Storage - High Piled, Solid Piled of Plastic and Rubber Commodity (Storage not to exceed 20' high, 100 sf, CMSA utilized see Sprinkler Specification) Future single and double row racks of Class I-IV commodities.
- Cooler #3 - High Piled, Class III Commodity Non-Encapsulate (Storage not to exceed 18' high 100 sf see NFPA 13: 14.2.4)
- Vat Room, Cultured Production, Cultured Packaging, Starter Room - Ordinary Hazard Group I (Storage not to exceed 8' high, 130 sf)
- Restrooms, Light Hazard
There is a wet system with an antifreeze loop, and a dry system.

Darigold - Tenant Improvement - This tenant improvement is to finish an approximate 22,000 sq. ft. area on the east end of the building, including Cooler Area #3, Cultured Packaging #107, Cultured Production #109, VAT Room #110 and Dry Storage #108. This permit also includes finishing two new restrooms #101 and #102, two 100 sq. ft. offices #103 & #104, CIP #105 and Storage #105A. Storage Room #105A is a control area constructed of one-hour fire-resistive construction. There are four control areas within the building. The remainder of the tenant improvement will be done under a separate permit. NOTE: THE H-3/H-4 OCCUPANCY STORATE AREAS ARE TO BE LOCATED AND CONSTRUCTED PRIOR TO OCCUPANCY OF THE PORTION OF THE BUILDING BEING FINISHED UNDER THIS PERMIT. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/23/20104/23/20104/26/2010APASS
DetailsForrest France
Fire sprinkler permit final approved.
INSP-Sprinkler Rough-in4/21/20104/21/20104/21/2010APART
DetailsForrest France
Forward flow testing completed satisfactory, recieved record drawings for field modifications.
INSP-Sprinkler Rough-in4/9/20104/9/20104/9/2010APART
DetailsForrest France
Noted correction items listed 4/1 verified for completion, rough-in passed.
INSP-Sprinkler Rough-in/Hydro4/5/20104/6/20104/6/2010APART
DetailsForrest France
Completed satisfactory hydrostatic test of the overhead wet systems including new and existing piping.
INSP-Sprinkler Rough-in/Hydro4/5/20104/5/20104/5/2010PPART
DetailsForrest France
INSP-Sprinkler Rough-in4/1/20104/1/20104/1/2010APART
DetailsForrest France
Completed overhead inspections at all new areas including the dry storage, east and west recieving, cooler #3, vat room, cultured packaging and production and dock. CIP room is not finished at this time, discussed hydrostatic testing schedule, noted a fire alarm permit to include new riser and antifreeze loop monitor points will be necessary. Red lined correction items on stamped plan set (seismic bracing, pend. outlet on dry system, etc.) including field modifications to be indicated on record drawings for relocated main, FDC, new SW heads. Riser needs tagged and head boxes mounted, RP and DCVA tested while on site.
INSP-Sprinkler Rough-in3/2/20103/3/20103/3/2010APART
DetailsForrest France
Inspection for fire resistive coatings at exposed wood surfaces above the drop ceilings at the new restroom entry vestibules.
INSP-Sprinkler Rough-in/Hydro2/26/20102/26/20102/26/2010PPART
DetailsForrest France
Concluded satisfactory 24 hr. air test @ 2:00PM 2/26 for overhead dry system install. Also okayed ceiling cover at the mens and womens restrooms and two new offices, new RR vestibules are not approved for cover due to pending fire resistive coatings at exposed wood.
INSP-Sprinkler Rough-in/Hydro2/25/20102/25/20102/26/2010PPART
DetailsForrest France
Begin 24 hr air testing of the new dry system piping at the SE cooler area at 50 psig. @ 2:00PM 2/25. Also completed hydrostatic testing of the new antifreeze loop at the north dock.
INSP-Sprinkler Rough-in/Hydro2/24/20102/24/20102/24/2010PPART
DetailsForrest France
Overhead hydrostatic testing for the new cooler area at the SE corner of the building completed satisfactory after repairs made while on site, noted insufficient seismic clearance at the main through the west wall- contractor to provide flex couplings spaced per NFPA 13 as discussed at this location.
INSP-Sprinkler Rough-in2/12/20102/12/20102/19/2010PPART
DetailsForrest France
On site visit regarding fire sprinkler coverage at the new restroom entry vestibules and concealed spaces. Included site walkthrough of building additions, dock areas, new wet riser and FDC at the east side. Discussed existing system and hydrostatic testing schedule.
INSP-Sprinkler Rough-in1/29/20101/29/20102/1/2010PPART
DetailsForrest France
Inspection for the new wet riser, DCVA, and UG riser okayed with the exception of insufficient clearance provision where the riser stub will meet the new floor slab- to be done prior to pour as discussed.
INSP-Conference2/1/20102/1/20102/1/2010ADONE
DetailsForrest France
Regarding UG supply pipe specs per NFPA ch. 8 and 10.