INSP-Final Inspection | 6/1/2010 | 6/2/2010 | 6/2/2010 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Accelerators have been installed and the two low air signals were received.
|
INSP-Sprinkler Rough-in | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Troy Cobbley
|
|
|
Forward flush passed.
|
INSP-Final Inspection | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | FAIL |
Troy Cobbley
|
|
|
The north and south dry pipe systems need accellerators per NFPA 13 - 7.2.3.3 since they exceed 500 gallons. The central system does have the accellerator but did not meet the 60 second rule as per NFPA 13- 7.2.3.2 since it has 755 gallons. Also see table 7.2.3.6.1. Still need to verify low air signal to the facp for the north system and the central system. A zone map is need showing the areas covered by each sprinkler system and the location of the control valves. All signals other than the two low air signals were sent and received at the fire alarm panel.
|
INSP-Final Inspection | 5/19/2010 | 5/19/2010 | 5/20/2010 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the two north most corridors and the residence rooms associated with them. All items were ok except quite a few canopies are falling off of the pendant heads. Lonnie said he would address the issue.
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2010 | 4/22/2010 | 4/22/2010 | P | PASS |
Troy Cobbley
|
|
|
The insulation has been replaced over the wet sprinkler piping in the south end of the building. The blow in insulation is ok to be installed.
|
INSP-Sprinkler Rough-in | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | PASS |
Troy Cobbley
|
|
|
The riser room and the adjacent electrical room are ok to cover.
|
INSP-Sprinkler Rough-in | 3/24/2010 | 3/25/2010 | 3/25/2010 | P | PASS |
Troy Cobbley
|
|
|
The three rooms near the nurses station are now ok to cover.
|
INSP-Sprinkler Rough-in | 3/24/2010 | 3/24/2010 | 3/24/2010 | P | FAIL |
Troy Cobbley
|
|
|
The tenting issues at the nurses station area have not been addressed. I spoke to Herb about what is needed to get a cover approval in this area.
|
INSP-Sprinkler Rough-in | 3/22/2010 | 3/23/2010 | 3/24/2010 | P | PART |
Troy Cobbley
|
|
|
The insulation blocking sprinkler coverage in the soffits has been addressed. All other areas in the lounge/hall areas, as discussed, can be covered. Three small rooms in the nurses station area can not be covered due to sprinkler pipe tenting issues.
|
INSP-Sprinkler Rough-in | 3/17/2010 | 3/17/2010 | 3/18/2010 | P | PART |
Forrest France
|
|
|
See annotations initialed with today's date on sheet FP-4 including the library, private dining, activity, and TV lounge rooms okayed for ceiling cover. NOTE: Soffits at the adjacent hallway and library/dining rooms are not yet approved for cover due to batt insulation blocking attic sprinkler coverage in these combustible pockets- Discussed solutions with contractor on site.
|
INSP-Sprinkler Rough-in | 3/16/2010 | 3/17/2010 | 3/17/2010 | A | CANC |
Troy Cobbley
|
|
|
Per telephone discussion with Lonnie this will be rescheduled for when the insulation is finished.
|
INSP-Sprinkler Rough-in | 3/10/2010 | 3/11/2010 | 3/11/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new locations where the sprinkler piping can be covered. Lonnie and I found the the south third of the building sprinkler piping covered without my cover inspections. I agreed for this one occation that instead of removing ceilings that I would access the piping in the attic as long as the insulation has been removed for inspection and then schedule a second inspection for the re-installation of the insulation.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2010 | 2/24/2010 | 2/24/2010 | P | PASS |
Troy Cobbley
|
|
|
The 24 hour air test on the last dry system passed.
|
INSP-Sprinkler Rough-in | 2/23/2010 | 2/23/2010 | 2/23/2010 | P | PART |
Forrest France
|
|
|
Begin 24 hour air test at the 4" dry valve at 3:30PM @48 psig.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2010 | 2/22/2010 | 2/22/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests of the last wet and dry system on the south end of the building passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2010 | 2/19/2010 | 2/19/2010 | A | FAIL |
Troy Cobbley
|
|
|
The last dry and wet system overhead hydro tests failed again. Will need to try again.
|
INSP-Sprinkler Rough-in | 2/17/2010 | 2/18/2010 | 2/18/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans marked with todays date for partial rough-in inspections on the last wet and dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2010 | 2/18/2010 | 2/18/2010 | A | FAIL |
Troy Cobbley
|
|
|
The last wet and dry system overhead hydro tests failed. There was visable leakage on the dry system.
|
INSP-Sprinkler Rough-in | 2/11/2010 | 2/12/2010 | 2/12/2010 | A | PASS |
Troy Cobbley
|
|
|
See the city approverd plans for locations with todays date for piping inspected. I The inspection included both wet and dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2010 | 2/11/2010 | 2/11/2010 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test of dry systems 3 and 4 and wet system 1 passed.
|
INSP-Sprinkler Rough-in | 2/10/2010 | 2/10/2010 | 2/10/2010 | P | PASS |
Troy Cobbley
|
|
|
The 24 hour air test on system 4 passed.
|
INSP-Sprinkler Rough-in | 2/8/2010 | 2/9/2010 | 2/10/2010 | P | PASS |
Troy Cobbley
|
|
|
The rough-in inspection for system 4 attic piping passed. Three baffles need installed as discussed. The 24 hour air test for system 4 was started at 2:00 with 52psi on the guage.
|
INSP-Sprinkler Rough-in | 1/28/2010 | 1/28/2010 | 1/28/2010 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations with todays date where sprinkler piping can be covered.
|
INSP-Conference | 1/22/2010 | 1/25/2010 | 1/25/2010 | A | DONE |
Troy Cobbley
|
|
|
Sprinkler pendant locations in relationship to pendant lights came into question. Per NFPA 13 and discussion with Tim Frost, the pendant lights will not be an issue.
|
INSP-Sprinkler Rough-in | 1/21/2010 | 1/22/2010 | 1/22/2010 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on dry system #3 passed. See the city approved plans where part of the sprinkler piping for wet system #1 can be covered.
|
INSP-Sprinkler Rough-in | 1/20/2010 | 1/21/2010 | 1/21/2010 | P | PART |
Troy Cobbley
|
|
|
The 24 hour air test was started at 11:00 with 44psi on the guage.
|
INSP-Sprinkler Rough-in | 1/14/2010 | 1/15/2010 | 1/15/2010 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the dry system #3. The rough-in is passed in general. The problems needing corrected include restraints are missing on the three branchlines over the kitchen area, through bolts are required for all of the earthquake connections to the wood members, the laterals and longitudinals can not be connected together unless calc'ed that way and 3/4" through bolts are required not the 3/8" as installed.
|