Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR09-00718
StatusFinaled
Name PEAK ALARM
Site Address 2740 S COLE RD Unit: 340
Project NameSHERWIN-WILLIAMS FLOORCOVERING
Customer Number 
ePlanReview 
Description
This fire alarm permit is to replace an existing dialer with a new FACP and an AES RF radio. The system will include a pull station and sprinkler system monitoring. No HVAC has been shown on the plans. Notification is not required, nor is part of this permit scope.

Associated building permit: BLD09-02035 (SHERWIN-WILLIAMS FLOORCOVERINGS) Suite 340. For minor tenant improvements to an existing 4,491 sq. ft. tenant space within an existing 19,120 sq. ft. building with work to include the construction of approximately 14 lineal feet of interior non-bearing partition wall with associated door and window dividing a larger office space into two smaller areas. No racking is included in this permit. Separate racking permits are required for any racking over 8 feet in height. This is a fully sprinklered building; any alterations to the existing sprinkler system will require a separate permit and shall comply with NFPA13 as regulated by the Boise City Fire Department. All work to be done per the approved plans. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/4/20101/4/20101/4/2010PPASS
DetailsTroy Cobbley
Permit finaled. The netcon rating was verified at 5 and all signals have been reverified.
INSP-Final Inspection12/24/200912/24/200912/24/2009PNR
DetailsForrest France
Not ready for final per phone call from contractor.
INSP-Alarm Testing12/22/200912/23/200912/23/2009PFAIL
DetailsStephanie L. Cobbley
(3:30pm 2nd inspection) Fire Alarm (NetCon) test failed. Rating reported a connectivity rating of 6. Minimum rating required per the manufacturers published installation instructions require a rating of 5 or less.

(11:30am 1st inspection) Fire Alarm inspection performed. At the time of this fire alarm inspection the building fire sprinkler system monitoring was verified by the central alarm monitoring facility. However, the Network Connectivity (NetCon) rating for the new AES transmitter component could not be verified by the field inspector because the applicant did not have in their possession the required tool to perform this test. The applicant agreed to return later in the afternoon, with the required tool, in order to perform the required (NetCon) test with the City field inspector. Final approval of this fire alarm permit is subject to satisfactory field inspection by the PDS/Fire inspector.