Permit Information
Permit NumberFIR09-00734
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 7235 W BETHEL ST
Project NameFarmers Brothers Coffee TI
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of providing fire protection to a portion of the building. The remainder portion of the building is supposed to be submitted at a later date under a separate permit. The portion of the building under this permit consists of a rectangular area of high piled rack storage. Storage is Coffee, Tea and Spices protected as a Class III commodity. The remaining portion of this permit is office area and ordinary hazard group II miscellaneous storage. The rack storage is described, as no plastics, including packaging, standard pallets, no shelves, 24' high single and double row racks with a minimum of 8' aisles. The review is based on NO idle pallet storage inside the building.

Plan Mod Scope:
The cross main was installed in a different location than what was shown on the original approved plans. New hydraulics were performed. The scope of work was slightly changed. There is a new upgrade agreement on file. There are slight sprinkler location modifications.


(FARMERS BROTHERS COFFEE) Permit is to remodel an existing 8,032 square foot office / warehouse building. UPGRADE AGREEMENT APPROVED FOR THIS BUILDING - agreement is attached to this case. Approval contingent upon adhering to the approved plans on file, attached engineering, and CZC09-00222. Work to include: [construction of interior non-bearing walls to create two fully accessible bathrooms, a new managers office, a fire sprinkler riser room, and to isolate off common area], installation of new accessible bathroom fixtures, installation of new hand sink, installation of new exterior landing, installation of new exterior loading ramp, installation of new opening in tilt-up wall, and finishes in compliance with chapter 8 of the 2006 IBC. This building is to be fully fire sprinklered per NFPA #13 as regulated by the fire department to comply with area requirements. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation (Racking permit # BLD09-02212). UPGRADE AGREEMENT APPROVED FOR THIS BUILDING - agreement is attached to this case. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/18/20103/19/20103/19/2010APASS
DetailsForrest France
Remainder of items per latest inspection activity verified for completion, some issues addressed while on site, fire sprinkler permit okay for final.
INSP-Final Inspection3/17/20103/18/20103/18/2010AFAIL
DetailsTroy Cobbley
Forward flush of the backflow needs to be performed, certification of the backflow, service tag on the riser, head box verified.....ect. The interconnection with the fire alarm panel tested ok. I spoke to Doug, the superintendant, and with Tom the building inspector about the need for the one hour riser room. Their are holes in the wall and gaps around all of the exiting piping.
INSP-Sprinkler Rough-in3/9/20103/9/20103/9/2010PPASS
DetailsTroy Cobbley
The rough-in inspection based on the resubmitted/as-builts passed. We could not gain access to the riser room for an inspection there.
INSP-Sprinkler Rough-in/Hydro3/7/20103/8/20103/8/2010APASS
DetailsTroy Cobbley
The overhead hydro test passed
INSP-Sprinkler Rough-in3/1/20103/2/20103/2/2010APART
DetailsTroy Cobbley
Plans need to be resubmitted showing the pipe routing changes and pipe size changes. These changes include the near main being relocated roughly 18' to the south and 3" riser nipples at all branchline/main connection points on both the near and far mains. The sprig ups are marked on the plans to be 1 1/4" but 1 1/2" have been installed. Insulation is laying on the upright sprinkler heads in several locations in the warehouse area. Two office areas near the riser room will have a combustible concealed space above the ceilings but Doug is going to cover with sheet rock. I gave the ok to cover some of the piping in the office area. See the approved plans for exact area.