INSP-Final Inspection | 3/15/2012 | 3/15/2012 | 3/15/2012 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
FIR-Aging Inspection | 1/20/2012 | 1/20/2012 | 1/23/2012 | | NR |
Troy Cobbley
|
|
|
I met with Tamara and Charlie and discussed the project status. The projects will be followed up on and their status relayed to me.
|
INSP-Final Inspection | 9/14/2011 | 9/14/2011 | 9/14/2011 | P | FAIL |
Troy Cobbley
|
|
|
The smoke/heat has been relocated and tested. Still need the firemans hat light addressed prior to a final sign off.
|
INSP-Final Inspection | 9/8/2011 | 9/9/2011 | 9/9/2011 | A | FAIL |
Stephanie L. Cobbley
|
|
|
Functionality of the recall and shunt trip functions passed, however the combination smoke/heat device at the top of the elevator shaft was located closer than 3' from the supply/return register and further than 2' from the sprinkler head, therefore it needs to be relocated. Also there is no fireman's hat light in the elevator, however there is an indicator light that remains solid regardless of the detector actuated. I let Colton know that if they can provide something in writing from the elevator contractor stating that the light is incapable of being made to flash that it would be acceptable due to the age of the elevator.
|
INSP-Conference | 9/1/2011 | 9/1/2011 | 9/1/2011 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Carl at ###-#### about getting this permit finaled. He is contacting simplex.
|
FIR-Aging Inspection | 12/13/2010 | 12/13/2010 | 12/16/2010 | | NR |
Troy Cobbley
|
|
|
Per Charlie this permit will be addressed
|
FIR-Aging Inspection | 4/29/2010 | 4/29/2010 | 4/30/2010 | | NR |
Troy Cobbley
|
|
|
Per Mark this project is acouple of months off due to the elevator being re-built.
|