Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR10-00061
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 850 W FRONT ST
Project NameBOISE CENTRE ON THE GROVE
Customer Number 
ePlanReview 
Description
7-1-10: PLAN MODIFICATION
This plan modification is to implement changes made in the field. The beam detector has been removed from the system, devices added and/or relocated, and notification candela rating increases.

2-24-10:
This fire alarm permit is to replace the existing fire alarm system with all new panels and devices. This permit scope includes partial area smoke detection (some with beam detectors), manual pull station, full notification (voice evacuation), HVAC monitoring, kitchen hood suppression system monitoring, sprinkler system monitoring, and door holder release. There is no associated building permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/2/20107/6/20107/6/2010APASS
DetailsForrest France
Notification and voice evac circuts and appliances tested satisfactory, verified plan resubmittals for field modifications, corrections per last site visit finished. Fire alarm permit finaled.
INSP-Final Inspection6/14/20106/21/20106/18/2010ACANC
DetailsForrest France
Call Lee ###-#### Inspection requested from web by: Mike Brown Phone #: ###-#### Inspection cancelled from web by: Mike Brown
INSP-Final Inspection5/28/20106/2/20106/2/2010AFAIL
DetailsForrest France
Items not repaired and included on the original inspection correction list include the duct detector at "Taters", missing signage at the door to the FACP room, sprinkler tamper switch must report as a supervisory condition. Also noted a trouble on the panel at one beam detector, overspaced and missing notification at the mechanical mezzanine, walkthrough completed for area B. Attempted an expedited test of the building alarm notification circuts by providing an additional inspector on site- test failed due to non-functional voice evacuation speakers at the main convention hall. A re-inspection fee will apply to the next site visit, see permit conditions for details.
INSP-Final Inspection5/27/20105/28/20105/27/2010ADEFR
DetailsForrest France
Mike Phone #: ###-#### Note: request intended for a different date per phone conversation.
INSP-Final Inspection5/17/20105/24/20105/25/2010AFAIL
DetailsForrest France
Correction items for areas inspected to date include; HVAC duct smoke detector at address L2-S29 in concessions room 210 "Perch" failed to initiate unit shut down- plan sheet F.A.2.1, duct smoke detector address L1-S29 in "Tators" failed to shut down HVAC unit, missing tamper switch and monitor module at the outside control valve for the fire sprinkler system- F.A. 2.3/2.0, missing one notification appliance at exhibit hall 200- sheet F.A.2.5, post signage at the door to the FACP room per review notes, notification devices have been changed from wall mount to ceiling mount at the restrooms F.A.2.5, incorrect cd setting at lockers 179, minor adjustments to as-built plans discussed, need clarification of room use at the "business center" area D as is lacking notification. Items inspected include kitchen hood monitoring, fire sprinkler riser supervision, heat detectors, manual pull station, area smoke detection at the basement, all duct detectors, door holds, walkthrough regarding notification appliance locations for areas A, C and D.