INSP-Final Inspection | 11/4/2010 | 11/4/2010 | 11/4/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/15/2010 | 10/15/2010 | 10/15/2010 | P | FAIL |
Troy Cobbley
|
|
|
Will be able to final when the insulation is repaired throughout the warehouse.
|
INSP-Final Inspection | 9/3/2010 | 9/7/2010 | 9/7/2010 | A | FAIL |
Troy Cobbley
|
|
|
The previous wall/draft stop/ needs to be removed out in the warehouse area and Storage Room 115 sprinkler pendants are too far down from the deck but still installed 8" above the t-bar/ceiling. Also in this room the flex ducting is creating alot of obstructions to the sprinkler coverage.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2010 | 8/4/2010 | 8/4/2010 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests of both systems passed.
|
INSP-Sprinkler Rough-in | 8/2/2010 | 8/2/2010 | 8/2/2010 | P | PART |
Troy Cobbley
|
|
|
Need to remove the smoke curtain/draft stop. Need hydro test. Need the "load splitters" hanger assemblies for the main addressed per tim frost. On closet on the second floor has a ceiling and has not been provided sprinkler protection. Also the sprinkler piping located above the first floor ceiling in the office area needs inspection.
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2010 | 7/30/2010 | 7/30/2010 | A | CANC |
Troy Cobbley
|
|
|
justin Phone #: ###-####//cancelled per Justin 7/30 @ 7:18am
|
INSP-Sprinkler Rough-in | 7/29/2010 | 7/29/2010 | 7/29/2010 | P | CANC |
Troy Cobbley
|
|
|
Cancelled due to time constraints caused by Micron plan review. Will be rescheduled for tomorrow per the fitter.
|