Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR10-00295
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 805 W IDAHO ST 200
Project NameBOISE CITY NATL BANK BLDG
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of adding, relocating sprinklers on portions of the first, second, and third floor. The new walls are wood and therefore above and below protection is required. The existing system is a tree with various pipe sizing. All pendent sprinklers on the second floor are being changed to quick response.

(The Caprock Group) - The fire sprinkler system substitutes for the 1-hr fire-resistance-rating of the building structure. To remodel an existing 4,000 square foot, office tenant space, on the second floor, of an existing building. Work to include: minor demolition per plans; construct new 2x4, wood, interior non-bearing, partition walls to create a storage room and an open office area; construct a partial height wall for an entry feature; related interior finishes in compliance with chapter 8 of the 2006 IBC; repair and replace existing ceiling system as required; upgrade the lighting layout; modify the existing exit lighting; plumbing, mechanical, and electrical work. All work per the approved plans, attached plan review report, and all other reviewing agencies approvals. NOTE: This building is fully fire sprinklered. Any alterations or modifications to the fire sprinkler system shall be per NFPA #13 as regulated by the fire department and will require a separate permit. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/6/20108/6/20108/6/2010PPASS
DetailsForrest France
Remainder of the scope of work and C/N items finished while on site and verified for completion. Fire sprinkler permit finaled.
INSP-Sprinkler Rough-in/Hydro8/5/20108/6/20108/6/2010APART
DetailsForrest France
Reinspection for previous correction items completed acceptable. However, noted fire sprinkler work at the third floor per plan had not been done, also missing an escutcheon at the first floor lobby.
INSP-Final Inspection8/3/20108/4/20108/5/2010AFAIL
DetailsForrest France
See activity notes dated 8/5
INSP-Final Inspection8/3/20108/4/20108/5/2010PFAIL
DetailsForrest France
See approved plans for locations of noted correction items at the second floor including missing escutcheons, overspaced heads at one office, missing QR head, lacking coverage at one closet. The existing system appears to be overdue a current annual inspection.
INSP-Sprinkler Rough-in/Hydro7/29/20107/29/20107/29/2010APART
DetailsForrest France
1st floor lobby okayed for cover.
INSP-Sprinkler Rough-in7/28/20107/28/20107/28/2010PPART
DetailsForrest France
Overhead work at the first floor lobby grid ceiling east side (3 pendents) is approved for cover.
INSP-Sprinkler Rough-in7/15/20107/16/20107/16/2010APASS
DetailsTroy Cobbley
2nd Flr Rough In passed. See the city approved plans for acouple of items that need corrected as marked in red. Piping is ok to cover.
INSP-Conference7/14/20107/14/20107/15/2010PDONE
DetailsForrest France
On site meeting regarding fire sprinkler coverage at the concealed spaces above the drop ceilings.
INSP-Sprinkler Rough-in7/14/20107/15/20107/15/2010APART
DetailsForrest France
Overhead rough-in at the main lobby 100 as per red lined area marked and initialed with today's date is approved for cover. Noted one pendent head at the rolled ceiling in close proximity to a junction box which may present an obstruction depending on type of light fixture installed.