INSP-Final Inspection | 8/26/2010 | 8/31/2010 | 8/31/2010 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/26/2010 | 8/31/2010 | 8/31/2010 | A | PASS |
Forrest France
|
|
|
Noted corrections field verified, fire alarm interconnects tested okay.
|
INSP-Final Inspection | 8/25/2010 | 8/26/2010 | 8/26/2010 | A | DEFR |
Forrest France
|
|
|
Rescheduled 8/31
|
INSP-Final Inspection | 8/11/2010 | 8/11/2010 | 8/11/2010 | P | FAIL |
Troy Cobbley
|
|
|
The earthquaking has been addressed and both of the risers easily passed the required forward flush. Per Lonnie the storage is being reduced to no higher than the designed 16' but was not complete yet. The fire alarm permit still needs to be addressed.
|
INSP-Sprinkler Rough-in | 8/9/2010 | 8/9/2010 | 8/9/2010 | P | FAIL |
Troy Cobbley
|
|
|
Sizing, placement and hangers for the new sprinkler piping was inspected and passed. The locations of the earthquake bracing does not match plans and in some locations the two way and four way braces are in switched locations. Also the maximum storage height is listed as 16'-0" but the storage is up to 19'-6" in several locations. Also no fire alarm permit has been applied/issued for the tamper switches and flow switches. This fire sprinkler permit will not be finaled until an alarm permit has been applied for. A forward flush test was not performed due to the design possibly being changed due to the new storage height. An above ground hydro test will not be required.
|