INSP-Final Inspection | 11/19/2010 | 11/19/2010 | 11/19/2010 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 11/8/2010 | 11/8/2010 | 11/8/2010 | P | FAIL |
Troy Cobbley
|
|
|
The testing of the bell passed. We are now waiting on a letter from the pump provider verifying that the correct gpm and psi has been provided. The letter will be sent to Tim Frost for verification prior to setting up another final inspection.
|
INSP-Final Inspection | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | FAIL |
Troy Cobbley
|
|
|
The inspector's test has not been set up to verify note "B" of the review comments. (two heads for 7 minutes). All other items appear ok.
|
INSP-Final Inspection | 11/1/2010 | 11/1/2010 | 11/1/2010 | P | CANC |
Troy Cobbley
|
|
|
Lonnie and my schedules did not meet. Rescheduled for tomorrow.
|
INSP-Sprinkler Rough-in | 8/31/2010 | 9/1/2010 | 9/1/2010 | A | PASS |
Troy Cobbley
|
|
|
The added pendants/piping, due to ceiling obstructions, is ok for cover.
|
INSP-Sprinkler Rough-in | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Per Lonnie and I's conversation, 8" lintels will be installed at the shower/soffit to avoid instlling sprinkler pendants in the showers.
|