INSP-Final Inspection | 9/8/2010 | 9/9/2010 | 9/9/2010 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/7/2010 | 9/8/2010 | 9/9/2010 | A | FAIL |
Troy Cobbley
|
|
|
Waiting for the project related fire alarm permit to be passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/7/2010 | 9/8/2010 | 9/8/2010 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test and forward flush passed.
|
INSP-Sprinkler Rough-in | 8/25/2010 | 8/26/2010 | 8/26/2010 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the drop ceiling areas can be covered.
|
INSP-Supply line flush | 8/23/2010 | 8/24/2010 | 8/24/2010 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush passed inspection.
|
INSP-Supply line flush | 8/19/2010 | 8/20/2010 | 8/20/2010 | P | FAIL |
Troy Cobbley
|
|
|
United water didnt unlock the valve again. No flushing performed.
|
INSP-Supply line flush | 8/18/2010 | 8/19/2010 | 8/19/2010 | P | FAIL |
Troy Cobbley
|
|
|
The underground had not been unlocked/turned on by United Water. No flushing was performed.
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2010 | 8/17/2010 | 8/17/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new antifreeze system passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2010 | 8/13/2010 | 8/13/2010 | P | PART |
Troy Cobbley
|
|
|
A partial rough-in was performed. The riser has not been built and arm overs/drops have not been installed yet. Pipe routing has been changed in the remote areas but after confering with Tim Frost resubmittals will not be required. See the city approved plans for locations of deficiencies as marked in red.
|
INSP-Supply line flush | 8/12/2010 | 8/13/2010 | 8/13/2010 | P | CANC |
Troy Cobbley
|
|
|
Water has not been turned on to site yet so no flush was performed.
|
INSP-Sprinkler Rough-in | 8/12/2010 | 8/13/2010 | 8/12/2010 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by John Venche Inspection cancelled from web by: John Venche
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2010 | 8/6/2010 | 8/6/2010 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line is ok to cover. The two 45 degree fittings have now been rodded.
|