Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR10-00358
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 457 E PARKCENTER BLVD
Project NameSage International School
Customer Number 
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of changing the existing fire protection to light hazard to protect the new school occupancy. Since there is change of occupancy the facilities fire protection must meet current code standards. An exception was given for no backflow preventer and seismic bracing due to being unreasonable per IFC: 104.8. If a backflow preventer was installed; the additional pressure loss from the backflow preventer would cause pipe size changes. The system is supplied with 4" underground, 4" riser and feed main. The branch lines are telescoping.

________________________________________

Building Department Scope:

This is an occupancy use change. To remodel an existing 11,200 sq. ft. office building changing occupancy to an educational school use per approved plans. Work to include select interior demolition of non-bearing walls & finishes (BLD10-01396); construction of new non-bearing walls to create classrooms, community room, library, computer/art and admin support areas. Install two, new, fully accessible restrooms and accessibility compliant drinking fountains; install cabinetry, sinks and modify plumbing, electrical, mechanical, sprinkler & alarm systems. NOTE: This building is fully fire sprinklered. PLAN MOD - 7/2/10 TO RELOCATE DOORS TO WOMEN'S RESTROOM FOR INSTALLATION OF (2) ADDITIONAL LAVS FOR CODE COMPLIANCE. Drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/16/201012/16/201012/17/2010PPASS
DetailsForrest France
Correction item field verified for completion. Fire sprinkler permit final approved.
INSP-Final Inspection11/4/201011/4/201011/4/2010APART
DetailsForrest France
New control valve on order per contractor.
INSP-Final Inspection8/23/20108/23/20108/23/2010APART
DetailsForrest France
INSP-Conference8/17/20108/17/20108/17/2010PPART
DetailsForrest France
Temporary occupancy approval okayed per M. Senteno.
INSP-Final Inspection8/10/20108/11/20108/11/2010PPART
DetailsForrest France
Final pending wall post indicator/butterfly valve interface approval. Remainder of the scope of work passed inspection.
INSP-Sprinkler Rough-in8/2/20108/3/20108/3/2010APART
DetailsForrest France
Correction items verified for completion, overhead fire sprinkler system modifications are good for cover at the drop ceiling.
INSP-Sprinkler Rough-in7/30/20107/30/20107/30/2010PFAIL
DetailsForrest France
See stamped plans on site for annotations and locations of correction items including one pendent head missing at classroom 129, blocked uprights at class 109, 1/2" extenders at drops in the community room 105, one leaking drop/armover at classroom 110.