INSP-Final Inspection | 1/11/2011 | 1/11/2011 | 1/12/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 1/2/2011 | 1/3/2011 | 1/3/2011 | A | CANC |
Troy Cobbley
|
|
|
not ready for final inspection
|
FIR-Aging Inspection | 12/27/2010 | 12/27/2010 | 12/27/2010 | | NR |
Troy Cobbley
|
|
|
This entry is being added from an original entry posted 12-22-10.
I found the the existing fire sprinkler system had been rendered inoperative in the north end of the building. I contacted Mark Sentenno and Gordan Goldsmith with the fire dept and let them know the situation. On site I spoke to the general contractor about the situation and he contacted the fire sprinkler contractor who was able to put the entire sprinkler system back in service within acouple of hours.
Upon last drive by the system was in service.
|