INSP-Final Inspection | 3/28/2011 | 3/28/2011 | 3/28/2011 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/16/2011 | 2/16/2011 | 2/16/2011 | P | CANC |
Troy Cobbley
|
|
|
I spoke to Jeff on the phone about the remaining items which are test papers, ventilation and emergency lighting in the pump room.
|
INSP-Sprinkler Rough-in/Hydro | 2/9/2011 | 2/9/2011 | 2/9/2011 | P | PASS |
Troy Cobbley
|
|
|
Hydro test passed. The 12 missing uprights have been added and the additional upright in the fire pump room has been provided. These items can be removed from the previous correction notice.
|
INSP-Final Inspection | 2/4/2011 | 2/7/2011 | 2/7/2011 | P | CANC |
Troy Cobbley
|
|
|
Permit is not ready for final. See "rough-in" inspection notes.
|
INSP-Sprinkler Rough-in/Hydro | 2/4/2011 | 2/7/2011 | 2/7/2011 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans/notes for items marked. They include pump room ventilation, pump room emergency lighting, additional sprinkler coverage in the pump room and 12 missing ESFR heads near the pump room and a hydro test.
|
INSP-Conference | 1/8/2011 | 1/11/2011 | 1/12/2011 | P | PASS |
Troy Cobbley
|
|
|
Certification of the fire pump passed. No other items inspected at this time.
|