INSP-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flush also passed
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2011 | 4/7/2011 | 4/7/2011 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2011 | 3/30/2011 | 3/30/2011 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit/building called in for inspection.
|
INSP-Sprinkler Rough-in | 3/23/2011 | 3/24/2011 | 3/24/2011 | A | PASS |
Forrest France
|
|
|
Passed one sprinkler in riser room as a rough in.
Steph Phone #: ###-####
|
INSP-Sprinkler Rough-in | 3/18/2011 | 3/22/2011 | 3/22/2011 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping on the second floor is ok to cover except at the new lobby area.
|
INSP-Sprinkler Rough-in | 3/15/2011 | 3/16/2011 | 3/16/2011 | A | PASS |
Troy Cobbley
|
|
|
The first floor sprinkler piping is ok to cover except at the Lobby area which has not been completed yet.
|
INSP-Sprinkler Rough-in | 3/1/2011 | 3/2/2011 | 3/2/2011 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was just for the rough-in on the second floor mains, branchlines and arm overs. Additional inspections will be required once the ceiling grid has been installed to verify final pendant sprinkler spacing.
|
INSP-Conference | 2/23/2011 | 2/24/2011 | 2/24/2011 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Sprinkler Rough-in | 2/23/2011 | 2/24/2011 | 2/24/2011 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was verifying that the combustible concealed spaces around the building have been reduced in size to be less than 160 cubic feet each as allowed in the 2009 NFPA 13. All of the spaces that were spot check on the outside of the building were 120 cubic feet or less and the second floor spaces were around 80 cubic feet. I gave the ok to re-cover the concealed spaces.
|
INSP-Sprinkler Rough-in | 2/23/2011 | 2/23/2011 | 2/23/2011 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow morning at 10am when all of the fire stopping has been completed per Jeff.
|
INSP-Sprinkler Rough-in | 2/22/2011 | 2/23/2011 | 2/23/2011 | A | PART |
Forrest France
|
|
|
jeff - ###-####
|
INSP-Sprinkler Rough-in | 2/9/2011 | 2/10/2011 | 2/10/2011 | A | PASS |
Troy Cobbley
|
|
|
Todays inspection was for cover in the hard lid areas. The piping in the hardlid areas marked "ok" is ok for cover.
|
INSP-Sprinkler Rough-in | 2/8/2011 | 2/9/2011 | 2/9/2011 | A | CANC |
Troy Cobbley
|
|
|
Cancelled due to time constraints. Message was left on voice mail.
|
INSP-Sprinkler Rough-in | 2/1/2011 | 2/1/2011 | 2/2/2011 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in.
|
INSP-Conference | 1/13/2011 | 1/14/2011 | 1/14/2011 | A | DONE |
Troy Cobbley
|
|
|
Jeff and I met and discussed the combustible concealed space/soffit that encircles the entire building. This space will need to meet NFPA 13 Chapter 8 requirements such as sprinkler protection or filled with non-combustible insulation.
|
INSP-Sprinkler Rough-in | 1/3/2011 | 1/4/2011 | 1/4/2011 | A | PASS |
Troy Cobbley
|
|
|
The insulation, in the second floor joist spaces, can be covered.
|
INSP-Sprinkler Rough-in | 12/22/2010 | 12/27/2010 | 12/27/2010 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the rough-in on the first floor. The piping as installed is ok except that resubmittals are required showing the pipe routing changes and the combustible construction. The combustible construction includes wall caps, beams, TJI joists, spaces under stairs, wall bracing and mechanical shafts. Per the plans the mechanical shafts are concrete. There is the possibility that the TJI's located on the first floor near the remote area will drive the need for the hydraulic calculations to utilize the 3,000sq ft remote area for the first floor. Fire sprinkler protection will need to be provided for both the first and second floors due to the combustibles or requirements out of NFPA 13 Chapter 8 will need to be met if possible. No piping is to be covered and no spaces are to be covered until these issues are resolved.
|
INSP-Sprinkler Rough-in | 12/9/2010 | 12/10/2010 | 12/10/2010 | A | FAIL |
Troy Cobbley
|
|
|
The insulation in the combustible concealed space does not meet 2010 NFPA 13 - 8.15.1.2.17. Blow-in insulation has been used not the batt insulation as required.
|