INSP-Final Inspection | 1/15/2013 | 1/16/2013 | 1/16/2013 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
FIR-Aging Inspection | 1/14/2013 | 1/14/2013 | 1/15/2013 | | NR |
Troy Cobbley
|
|
|
|
FIR-Aging Inspection | 9/24/2012 | 9/24/2012 | 10/1/2012 | | NR |
Troy Cobbley
|
|
|
Forwarded information to Scott for further action.
|
FIR-Aging Inspection | 4/26/2012 | 4/26/2012 | 5/2/2012 | | NR |
Troy Cobbley
|
|
|
Charlie is going to schedule Dante to finishs the as-builts.
|
FIR-Aging Inspection | 1/20/2012 | 1/20/2012 | 1/23/2012 | | NR |
Troy Cobbley
|
|
|
I met with Tamara and Charlie and discussed the project status. The projects will be followed up on and their status relayed to me.
|
FIR-Aging Inspection | 4/27/2011 | 4/27/2011 | 5/5/2011 | | NR |
Troy Cobbley
|
|
|
I spoke to Tammy with SimplexGrinnell about getting work completed and the inspection finaled. She is following up and will contact me with the project status.
|
INSP-Final Inspection | 2/10/2011 | 2/16/2011 | 2/16/2011 | A | FAIL |
Troy Cobbley
|
|
|
Provide signage at the inoperative firemans controls in both elevators as discussed or make all functions operational.
|
INSP-Final Inspection | 1/28/2011 | 2/9/2011 | 2/9/2011 | A | CANC |
Troy Cobbley
|
|
|
The contractor did not have the city approved job site copy plans on site. No inspection was performed.
|