INSP-Final Inspection | 4/25/2011 | 4/25/2011 | 4/26/2011 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection per T. Frost.
|
INSP-Final Inspection | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Forrest France
|
|
|
Final passed and forward flow test passed.
don Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Forrest France
|
|
|
Overhead hydro passed on both floors.
don Phone #: ###-####
|
INSP-Final Inspection | 4/19/2011 | 4/20/2011 | 4/21/2011 | A | NR |
Forrest France
|
|
|
Provide sprinkler coverage at the second floor patio room, records indicate an overhead hydrostatic test remains, FDC appears partially obstructed. Outside bell repaired while on site.
|
INSP-Final Inspection | 4/19/2011 | 4/19/2011 | 4/20/2011 | P | NR |
Forrest France
|
|
|
Don Phone #: ###-####
|
INSP-Final Inspection | 3/25/2011 | 3/25/2011 | 3/25/2011 | P | NR |
Tim Frost
|
|
|
Fire alarm was not ready.
don Phone #: ###-####
|
INSP-Supply line flush | 3/25/2011 | 3/25/2011 | 3/25/2011 | P | PASS |
Tim Frost
|
|
|
Flush completed successfully.
don Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2011 | 3/8/2011 | 3/8/2011 | P | DONE |
Tim Frost
|
|
|
Hydro passed.
Rough in passed except for adding one brace to the main where a new offset was added. The hydraulics had enough cushion that the offset did not adversely affect the hydraulic calculation. One drop plug in restroom awaiting ceiling.
|
INSP-Conference | 3/2/2011 | 3/2/2011 | 3/3/2011 | P | DONE |
Forrest France
|
|
|
Site visit regarding suspended light fixture placement at the east side main level. Upright sprinkler protection does not appear obstructed as currently installed.
|
INSP-Sprinkler Rough-in/Hydro | 1/19/2011 | 1/20/2011 | 1/20/2011 | A | PART |
Forrest France
|
|
|
Restrooms okayed for ceiling cover. Noted missing hangers one branch piece per line at the deck, inspectors test connections at the riser to be relocated. Full rough-in inspection not complete.
|