INSP-Final Inspection | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | PASS |
Forrest France
|
|
|
C/N items finished, re-inspection passed. Final okay pending scanable as-built record drawings are provided including an accurate map at the panel.
|
INSP-Final Inspection | 12/27/2010 | 12/27/2010 | 12/28/2010 | P | PART |
Forrest France
|
|
|
Adjustments for final include; provide as-built drawings accurately reflecting field installation including duct detectors at RTUs 5 and 7, the deletion of one KH monitor, provide a strobe only at the wine/av room, amend visual coverage at lounge 108 due to obstruction by ceiling suspended finishes, provide a lock at the FACP circut breaker, post accurate map at the panel. Remainder of fire alarm work tested satisfactory.
|
INSP-Final Inspection | 12/8/2010 | 12/9/2010 | 12/9/2010 | A | PART |
Forrest France
|
|
|
Hood suppression and fire sprinkler riser system interconnections tested okay, offsite monitoring verified. Minor corrections and account information adjustments done while on site.
|