INSP-Final Inspection | 1/25/2012 | 1/27/2012 | 1/27/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. As-builts to be turned in.
|
INSP-Conference | 1/23/2012 | 1/23/2012 | 1/23/2012 | P | DONE |
Troy Cobbley
|
|
|
I met with Tamara and Charlie and discussed the project status. The projects will be followed up on and their status relayed to me.
|
INSP-Conference | 1/12/2012 | 1/12/2012 | 1/12/2012 | P | DONE |
Troy Cobbley
|
|
|
Colton had questions concerning the firemans hat light. I deferred the question to the fire alarm plan reviewer.
|
FIR-Aging Inspection | 1/12/2012 | 1/12/2012 | 1/12/2012 | | NR |
Troy Cobbley
|
|
|
Still waiting for simplexgrinnell to correct the elevator recall functions.
|
INSP-Final Inspection | 7/5/2011 | 7/6/2011 | 7/6/2011 | A | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when the elevator recall functions have been corrected or an upgrade agreement with the Boise Fire Dept. has been reached.
|
INSP-Final Inspection | 7/1/2011 | 7/5/2011 | 7/5/2011 | A | FAIL |
Troy Cobbley
|
|
|
The horn located at the north stairwell door makes a continuous tone and not temporal. Per Colton this device should be on a new circuit.
|
INSP-Final Inspection | 7/1/2011 | 7/1/2011 | 7/1/2011 | P | FAIL |
Troy Cobbley
|
|
|
The strobe in room 225 failed to function and the elevator, as per previous discussions, needs to be addressed.
|
INSP-Sprinkler Rough-in | 5/19/2011 | 5/20/2011 | 5/20/2011 | A | DONE |
Troy Cobbley
|
|
|
The strobes in two additional exam rooms functioned correctly. Marked ok on the plans.
|
INSP-Sprinkler Rough-in | 4/28/2011 | 4/29/2011 | 4/29/2011 | A | PART |
Troy Cobbley
|
|
|
Phase 3 and 5 are complete
|
INSP-Sprinkler Rough-in | 3/29/2011 | 3/29/2011 | 3/29/2011 | P | CANC |
Troy Cobbley
|
|
|
Wrong inspection type was called in. This was actually for alarm testing.
|
INSP-Alarm Testing | 3/29/2011 | 3/29/2011 | 3/29/2011 | P | DONE |
Troy Cobbley
|
|
|
The phase II fire alarm testing is complete. An item noted was any general smoke detector alarm would recall the elevator which is not allowed. I agreed to "sign off" for this phase II work but the elevator recall will need to be addressed prior to a final sign off on this project.
|
INSP-Alarm Testing | 2/16/2011 | 2/17/2011 | 2/17/2011 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for devices marked ok that have been tested and passed. Research is needed to verify that the temporal signal "timing" meets NFPA 72.
|
INSP-Sprinkler Rough-in | 2/8/2011 | 2/9/2011 | 2/9/2011 | A | CANC |
Troy Cobbley
|
|
|
bryan Phone #: ###-####
|