Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberFIR11-00016
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3214 E AMITY RD
Project NameRocky Mountain Packaging
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing fire protection in a new office area and a loading dock area. The existing building is apparently missing fire protection in some areas. Fire protection is being added to these areas at this time so that the building is a fully sprinklered building. The existing is a 4”x2½”x1¼” grid with 6” underground, 6” riser with a 6” backflow preventer and wall PIV.

History:
Based on the IFC report for permit BLD10-01287 The building will store plastic packaged of pills (3-4 pills in a plastic pack) in cardboard boxes to a maximum height of 8’, anything higher than 8’ will require a complete sprinkler system reevaluation.


Building Department Scope:

Rocky Mountain Packaging - Office and Warehouse Loading Area Additions - To construct a new 1,120 square foot, one story, wood framed office addition with a 120 square foot covered patio on the east side of an existing 11,165 square foot, one story manufacturing building. This permit is also to construct a 500 square foot, one story wood framed loading area addition on the north side of the existing fabrication building. This permit also includes related site improvements. This building is fully fire sprinkled, the sprinklers are used for area increase. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/9/20112/10/20112/10/2011APASS
DetailsForrest France
Recieved as-built plans from contractor regarding deleted head at the covered patio per NFPA 13 2007 8.15.7.3(1) exception. C/N items finished, permit finaled.
INSP-Final Inspection2/9/20112/10/20112/9/2011ACANC
DetailsForrest France
jason Phone #: ###-#### Inspection cancelled from web by: Stan Beus
INSP-Final Inspection2/4/20112/7/20112/7/2011AFAIL
DetailsForrest France
Missing escutcheons at the new office areas, covered head at one closet, patio at the north side is still missing a sidewall head- provide coverage per plan or document with a plan modification including reason deleted.
INSP-Sprinkler Rough-in/Hydro1/27/20111/27/20111/27/2011PPASS
DetailsTim Frost
Hydro Passed.
Lower office area not previously inspected was ok to cover.
INSP-Sprinkler Rough-in1/21/20111/24/20111/24/2011APART
DetailsForrest France
Overhead okayed for cover at the east side addition sheetrock ceiling. Missing sw head per plan at the covered patio. Remainder of work scope incomplete at this time.