INSP-Final Inspection | 10/27/2011 | 10/27/2011 | 10/27/2011 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | PART |
Forrest France
|
|
|
Verified temporary partitions have been removed. Added heads at the open areas adjacent to the new remodel okayed. Final pending installation of the remainder of ceiling tile and escutcheons.
|
INSP-Final Inspection | 10/7/2011 | 10/10/2011 | 10/10/2011 | P | CANC |
Troy Cobbley
|
|
|
Please calL Jeremy with time frame. ###-####. Thanks >> Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 9/29/2011 | 9/29/2011 | 9/29/2011 | P | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in/Hydro | 9/15/2011 | 9/15/2011 | 9/16/2011 | P | PART |
Forrest France
|
|
|
Pendent heads at the sheetrock ceiling area as marked on stamped plans okayed for cover.
|
INSP-Sprinkler Rough-in | 5/25/2011 | 5/25/2011 | 5/25/2011 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 | A | PART |
Forrest France
|
|
|
Work to date okayed for cover.
|
INSP-Sprinkler Rough-in | 3/4/2011 | 3/4/2011 | 3/4/2011 | A | PART |
Forrest France
|
|
|
East and west 1st floor lower focus rooms and BU 2nd floor focus rooms only- remainder of permit work incomplete at this time.
|