INSP-Final Inspection | 4/4/2011 | 4/5/2011 | 4/5/2011 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Final Inspection | 3/31/2011 | 4/1/2011 | 4/1/2011 | P | PART |
Forrest France
|
|
|
Reinspection items passed. Final pending repair of one damper motor at the 3rd floor.
|
INSP-Alarm Testing | 3/30/2011 | 3/30/2011 | 3/30/2011 | P | PART |
Forrest France
|
|
|
Final pending noted corrections.
|
INSP-Final Inspection | 3/25/2011 | 3/29/2011 | 3/29/2011 | P | PART |
Forrest France
|
|
|
Fire alarm testing completed. Items needed for final include powered dampers at the third floor to verify operation, repair existing notification device at the 2nd floor comm. room, relocate MPat the main entry vestibule 1st floor, replace/add horns at the basement mechanical room, provide signage at the door to the FACP room per review note #21.
|
INSP-Conference | 3/18/2011 | 3/18/2011 | 3/18/2011 | P | DONE |
Forrest France
|
|
|
On site meeting with general contractor regarding fire alarm work in progress, review notes, red-line comments, appliance locations, testing schedule, code requirements, etc.
|