Permit Information
Permit NumberFIR11-00167
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 11197 W FAIRVIEW AVE
Project NamePrimary Health - Wildwood
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing a new wet pipe system above and below the ceiling for a new office/medical facility. The system is a tree type system with 6” underground approved under permit FIR11-00130. The tree type system utilizes a 2” main with 1¼" branch lines. The main riser and backflow preventer is 2½”. The single floor building construction has wood trusses and there is a high bay at the main entrance.


Building Department Scope:

Primary Health - To construct a new 5,275 square foot, one story, wood framed medical office building and related site improvements. This building will contain a reception and waiting area, offices, exam rooms, x-ray room, procedure room, five accessible restrooms and a break room. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/15/20118/16/20118/16/2011PPASS
DetailsTroy Cobbley
Permit finaled. The forward flush passed.
INSP-Final Inspection8/12/20118/15/20118/15/2011PFAIL
DetailsTroy Cobbley
Need the backflow certified and forward flow tested. Also the two upright heads in the riser room are too far below the ceiling.
INSP-Sprinkler Rough-in/Hydro7/15/20117/18/20117/18/2011APASS
DetailsTroy Cobbley
The above ground hydro test passed and the corrections have been made to the above ground piping. Piping can be covered.
INSP-Sprinkler Rough-in/Hydro7/13/20117/14/20117/14/2011AFAIL
DetailsTroy Cobbley
The hydro test could not be performed due to additional upright heads required around the x-ray room and on the back side of the roof access door. Also the most current set of plans was not on site.
INSP-Sprinkler Rough-in6/8/20116/8/20116/8/2011PPASS
DetailsTroy Cobbley
Rough-in passed and piping can be covered in the Entry area.
INSP-Sprinkler Rough-in6/6/20116/7/20116/7/2011PPASS
DetailsTroy Cobbley
Hard lid ceiling areas are ok for cover.