Name VIKING AUTOMATIC SPRINKLER CO
Site Address 1301 N ORCHARD ST STE 200
Project NameCSC BUILDING
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of renovating the sprinkler system on the second floor of a two-floor building. The building has solid wood joist in the attic with dry wall tight to the bottom of the joist. The joists are filled with insulation. The building has two underground supplies and two risers; one east and one west. The majority of the second floor sprinkler system is being demo and replaced. The eastern half is 2”x2”x1¼” grid with a 3” feed main. The western half is a tree with 1”, 1¼", 1½” lines and 2” main. All new sprinklers to be quick response type.

Plan Mod Scope:
The plan mode scope of work includes adding three sprinklers in a soffit due to obstructions caused by ductwork. In addition, seven upright sprinklers are being added due to walls going to the deck for soundproofing instead of the ceiling. The walls cause obstruction issues to the existing upright sprinklers.


Building Department Scope:

The fire sprinkler is used for area and height increase. To remodel a 15,330 square foot area on the 18,722 square foot 2nd story of an existing building for a new office tenant. Work is to include interior nonbearing walls, 2 restrooms accessible to the disabled, an interior 3 riser stairway, an interior ramp accessible to the disabled, suspended acoustical ceilings, interior doors, interior windows, and finishes. Two skylights will be removed and the roof opening filled in with roof joists and roof sheathing. The roof covering and roof insulation are allowed to match the existing conditions. A stairway will be removed and the floor opening filled in with floor joists and floor sheathing. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/19/20118/22/20118/22/2011PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/15/20118/18/20118/18/2011APART
DetailsForrest France
Items which remain for final include; provide spare heads at the head box of the type installed, certify the DCVA, re-test alarm and supervisory conditions at the riser. Final walkthrough completed acceptable.
INSP-Sprinkler Rough-in/Hydro8/2/20118/2/20118/2/2011PPASS
DetailsTroy Cobbley
Hydro test passed. Second floor piping can be covered.
INSP-Sprinkler Rough-in6/23/20116/24/20116/24/2011APART
DetailsForrest France
Added upright sprinklers at the east end open office area soffit (due to ductwork obstructions) as marked and dated on approved plans okay for cover.
INSP-Sprinkler Rough-in/Hydro6/20/20116/22/20116/23/2011ADONE
DetailsForrest France
Reference site inspection notes per T. Frost completed 6/22.
INSP-Sprinkler Rough-in/Hydro6/22/20116/23/20116/22/2011AFAIL
DetailsTroy Cobbley
Second floor only. The hydro passed. However, I also inspected the uprights in the soffit. Some of the sprinkers were blocked due to ductwork. Additional, sprinklers are required. Therefore the inspection failed.