Permit NumberFIR11-00301
StatusFinaled
Name ALLIED GENERAL FIRE & SECURITY
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer NumberC15044
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of system 8 ONLY. This system protects approximately half of the subfab area (lower level). The sprinklers are space at the junction of the concrete waffle construction. The system is a 4”x4”x1½” grid. The system is supplied by two 8” connections to a 10” loop underground. The two 8” lead ins are equipped with a yard PIV. A free standing FDC on top of a pit is also included in this scope of work. There is additional fire protection below three large ducts running east to west due to obstruction issues.

Plan Mod #1
The underground supply feeding the north riser was changed from a loop supply into the building to a dead end feed into the building. The north riser was revised accordingly.


Building Department Scope:

Micron Building B50 - R&D Building - To construct a new 111,005 square foot, two story, with 71,855 square foot basement, concrete and steel semiconductor fabrication R & D facility and related site improvements. The first floor level is 89,435 sq. ft. (60,100 sq. ft. finished and 29,325 sq. ft. unfinished). The second floor is a 21,570 sq. ft. mechanical space (16,170 sq. ft. used and 5,400 square feet future). The basement level (subfab.) has 43,295 sq. ft. finished and 28,560 unfinished. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/20/201211/20/201211/20/2012APASS
DetailsForrest France
INSP-Final Inspection10/22/201210/22/201210/30/2012PPEND
DetailsForrest France
Ref. activity notes.
INSP-Final Inspection10/17/201210/19/201210/30/2012APART
DetailsForrest France
Noted overspaced coverage at one location below ductwork at the junction between sub fab systems, provide verification AE and FE ductwork does not require protection per IFC 2009 1803.10.4 (1-3).
FIR-Aging Inspection8/28/20128/28/20128/28/2012 DEFR
DetailsForrest France
INSP-Supply line flush5/29/20125/30/20125/30/2012PPART
DetailsForrest France
UG fire supply line flush for the SW building riser and remote FDC completed satisfactory.
INSP-Sprinkler Rough-in4/10/20124/11/20124/12/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in4/2/20124/3/20124/4/2012PPART
DetailsForrest France
Vestibules 000B and 002B are incomplete. Plan modifications pending.
INSP-Sprinkler Rough-in/Hydro3/30/20124/2/20124/2/2012PPART
DetailsForrest France
Overhead hydrostatic test passed.
INSP-Sprinkler Rough-in/Hydro3/29/20123/30/20123/30/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro3/28/20123/29/20123/30/2012AFAIL
DetailsForrest France
Overhead hydrostatic test failed due to pressure loss at the gauge.
INSP-Sprinkler Rough-in/Hydro2/28/20122/29/20123/1/2012PPART
DetailsForrest France
Re-inspection for corrections system 8 sub fab include the following locations: added coverage at extended ductwork, over spacing at sub fab mechanical, coverage added at the catwalk and soffits between elevator machine room 001A and communication room 001B.
INSP-Sprinkler Rough-in/Hydro2/20/20122/21/20122/22/2012APART
DetailsForrest France
System 8 sub fab reinspection items include spacing at the temporary wall is 7'-6", four obstructed uprights adjacent to temporary unistrut trapeeze members, added outlet for chemical cabinets not shown on plans, missing potter air vent per drawings, added vestibules 000B and 002B including fire protection are not included on plans, sheetrock soffit enclosure at the new catwalk creates obstructions in three areas, need to add coverage under newly extended ductwork over 4', missing intermediate hangers under both stairways. Noted overspaced uprights under ductwork system 8 mechanical. Previous c/n items at some areas have been completed. Also noted quantities of sodium hypochlorite, sulfuric acid, process water, DI and IW located within the building.
INSP-Sprinkler Rough-in1/11/20121/12/20121/12/2012APART
DetailsForrest France
UG fire supply line flush at the NW riser feed completed satisfactory.
INSP-Supply line flush1/10/20121/11/20121/11/2012PNR
DetailsForrest France
Contractor unable to complete supply line flushing at the NW riser due to jobsite conditions.
INSP-Sprinkler Rough-in/Hydro11/22/201111/23/201111/23/2011PNR
DetailsForrest France
Please contact Jeremiah prior to arrival. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley NOTE: **Area requested for inspection is not included in the scope of this permit (FIR11-00301 covers system 8 sub-fab). Contractor intended an overhead inspection for system 4 photo bay for which permit FIR11-00524 is not yet approved or issued at this time. Noted system 4 mains and branchlines already installed. No inspection performed due to permit status and lack of approved drawings.**
INSP-Sprinkler Rough-in11/21/201111/21/201111/21/2011PPART
DetailsForrest France
UG fire supply line and remote FDC piping at the NW corner inspected prior to cover. Contractor has installed mechanical joint restraints in place of thrust blocks.
INSP-Sprinkler Rough-in/Hydro11/18/201111/21/201111/21/2011APART
DetailsForrest France
UG hydrostatic test for the NW fire supply line and remote FDC piping completed satisfactory.
INSP-Sprinkler Rough-in/Hydro11/18/201111/18/201111/18/2011PNR
DetailsForrest France
Please call Jeremiah prior arrival to confirm. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley
INSP-Sprinkler Rough-in11/14/201111/15/201111/15/2011APART
DetailsForrest France
UG fire supply line and remote FDC piping at the SE corner okayed to bury. Note: contractor has utilized a restrained joint system per NFPA 13 10.8.3 in place of thrust blocking. Discussed bury depth requirements with contractor per civil drawing elevations- UG pipe to be maintained 4'6" below grade min.
INSP-Sprinkler Rough-in/Hydro11/11/201111/14/201111/14/2011APART
DetailsForrest France
UG fire supply line and remote FDC piping at the SE corner of building 50 passed hydrostatic test.
INSP-Sprinkler Rough-in/Hydro11/9/201111/10/201111/10/2011AFAIL
DetailsTroy Cobbley
tony please call 1/2 hr prior Phone #: ###-####

Contacted tony and let him know I was on the way. I arrived and found that the water had not been turned on for tony to pump up the underground. No testing was performed.
INSP-Conference8/12/20118/15/20118/15/2011ADONE
DetailsForrest France
On site conference with contractor regarding project design, installation, schedule, etc.