INSP-Final Inspection | 11/20/2012 | 11/20/2012 | 11/20/2012 | A | PASS |
Forrest France
|
|
|
|
INSP-Final Inspection | 10/22/2012 | 10/22/2012 | 10/30/2012 | P | PEND |
Forrest France
|
|
|
Ref. activity notes.
|
INSP-Final Inspection | 10/17/2012 | 10/19/2012 | 10/30/2012 | A | PART |
Forrest France
|
|
|
Noted overspaced coverage at one location below ductwork at the junction between sub fab systems, provide verification AE and FE ductwork does not require protection per IFC 2009 1803.10.4 (1-3).
|
FIR-Aging Inspection | 8/28/2012 | 8/28/2012 | 8/28/2012 | | DEFR |
Forrest France
|
|
|
|
INSP-Supply line flush | 5/29/2012 | 5/30/2012 | 5/30/2012 | P | PART |
Forrest France
|
|
|
UG fire supply line flush for the SW building riser and remote FDC completed satisfactory.
|
INSP-Sprinkler Rough-in | 4/10/2012 | 4/11/2012 | 4/12/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/2/2012 | 4/3/2012 | 4/4/2012 | P | PART |
Forrest France
|
|
|
Vestibules 000B and 002B are incomplete. Plan modifications pending.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2012 | 4/2/2012 | 4/2/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2012 | 3/30/2012 | 3/30/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2012 | 3/29/2012 | 3/30/2012 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to pressure loss at the gauge.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2012 | 2/29/2012 | 3/1/2012 | P | PART |
Forrest France
|
|
|
Re-inspection for corrections system 8 sub fab include the following locations: added coverage at extended ductwork, over spacing at sub fab mechanical, coverage added at the catwalk and soffits between elevator machine room 001A and communication room 001B.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2012 | 2/21/2012 | 2/22/2012 | A | PART |
Forrest France
|
|
|
System 8 sub fab reinspection items include spacing at the temporary wall is 7'-6", four obstructed uprights adjacent to temporary unistrut trapeeze members, added outlet for chemical cabinets not shown on plans, missing potter air vent per drawings, added vestibules 000B and 002B including fire protection are not included on plans, sheetrock soffit enclosure at the new catwalk creates obstructions in three areas, need to add coverage under newly extended ductwork over 4', missing intermediate hangers under both stairways. Noted overspaced uprights under ductwork system 8 mechanical. Previous c/n items at some areas have been completed. Also noted quantities of sodium hypochlorite, sulfuric acid, process water, DI and IW located within the building.
|
INSP-Sprinkler Rough-in | 1/11/2012 | 1/12/2012 | 1/12/2012 | A | PART |
Forrest France
|
|
|
UG fire supply line flush at the NW riser feed completed satisfactory.
|
INSP-Supply line flush | 1/10/2012 | 1/11/2012 | 1/11/2012 | P | NR |
Forrest France
|
|
|
Contractor unable to complete supply line flushing at the NW riser due to jobsite conditions.
|
INSP-Sprinkler Rough-in/Hydro | 11/22/2011 | 11/23/2011 | 11/23/2011 | P | NR |
Forrest France
|
|
|
Please contact Jeremiah prior to arrival. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley NOTE: **Area requested for inspection is not included in the scope of this permit (FIR11-00301 covers system 8 sub-fab). Contractor intended an overhead inspection for system 4 photo bay for which permit FIR11-00524 is not yet approved or issued at this time. Noted system 4 mains and branchlines already installed. No inspection performed due to permit status and lack of approved drawings.**
|
INSP-Sprinkler Rough-in | 11/21/2011 | 11/21/2011 | 11/21/2011 | P | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the NW corner inspected prior to cover. Contractor has installed mechanical joint restraints in place of thrust blocks.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2011 | 11/21/2011 | 11/21/2011 | A | PART |
Forrest France
|
|
|
UG hydrostatic test for the NW fire supply line and remote FDC piping completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2011 | 11/18/2011 | 11/18/2011 | P | NR |
Forrest France
|
|
|
Please call Jeremiah prior arrival to confirm. Phone #: ###-#### >> Inspection requested via web by Alicia Pauley
|
INSP-Sprinkler Rough-in | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the SE corner okayed to bury. Note: contractor has utilized a restrained joint system per NFPA 13 10.8.3 in place of thrust blocking. Discussed bury depth requirements with contractor per civil drawing elevations- UG pipe to be maintained 4'6" below grade min.
|
INSP-Sprinkler Rough-in/Hydro | 11/11/2011 | 11/14/2011 | 11/14/2011 | A | PART |
Forrest France
|
|
|
UG fire supply line and remote FDC piping at the SE corner of building 50 passed hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2011 | 11/10/2011 | 11/10/2011 | A | FAIL |
Troy Cobbley
|
|
|
tony please call 1/2 hr prior Phone #: ###-####
Contacted tony and let him know I was on the way. I arrived and found that the water had not been turned on for tony to pump up the underground. No testing was performed.
|
INSP-Conference | 8/12/2011 | 8/15/2011 | 8/15/2011 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding project design, installation, schedule, etc.
|