INSP-Final Inspection | 9/6/2011 | 9/7/2011 | 9/7/2011 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection.
|
INSP-Final Inspection | 9/2/2011 | 9/2/2011 | 9/2/2011 | P | FAIL |
Forrest France
|
|
|
Final pending repair of three non-functional waterflow switches at the new riser manifold.
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2011 | 8/12/2011 | 8/12/2011 | P | PART |
Forrest France
|
|
|
Hydrostatic testing passed for the new wet system manifolds and piping.
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2011 | 8/12/2011 | 8/12/2011 | A | PART |
Forrest France
|
|
|
Overhead rough-in for the new dry system completed. Noted items include; replace three BB1 attic heads due to modified deflector/frame orientation, one upright head at the NE dormer is obstructed by truss webs, one EQ brace secured while on site.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2011 | 8/11/2011 | 8/12/2011 | A | PART |
Forrest France
|
|
|
Completed satisfactory 24 hr. air test of the new dry system piping.
|
INSP-Final Inspection | 8/9/2011 | 8/10/2011 | 8/10/2011 | A | PART |
Forrest France
|
|
|
Begin 24 hr. air test of the new dry system piping at 11:30 AM @44.5psig.
|
INSP-Sprinkler Rough-in/Hydro | 8/8/2011 | 8/9/2011 | 8/9/2011 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing for the new dry system piping passed. Discussed schedule for pneumatic test.
|