INSP-Final Inspection | 10/17/2011 | 10/17/2011 | 10/17/2011 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/11/2011 | 10/12/2011 | 10/12/2011 | A | FAIL |
Troy Cobbley
|
|
|
Signals are now being reported correctly. As-builts/Intelipro information was not provided as requested by plan review.
|
INSP-Final Inspection | 9/30/2011 | 9/30/2011 | 9/30/2011 | P | FAIL |
Troy Cobbley
|
|
|
Tested the flow switch, tamper #1 and main lobby pull station. Paul received the signals from the relays but no informaton from the intela tap came in.
|
INSP-Final Inspection | 9/28/2011 | 9/28/2011 | 9/28/2011 | P | FAIL |
Troy Cobbley
|
|
|
Tamper #1 needs adjusted, could not find the inspectors test valve so the flow switch was not tested. Also need the tamper switch and manual pull stations addresses on the panel to match the map and what is reported to central station. All other items were tested. Horns did not sync but Gary fixed this while I waited.
|
INSP-Final Inspection | 9/26/2011 | 9/26/2011 | 9/26/2011 | P | FAIL |
Troy Cobbley
|
|
|
Did not perform the testing due to the intella tap not being installed on the AES dialer.
|
INSP-Final Inspection | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for locations of corrections needed. No actual testing was performed
|
INSP-Conference | 8/31/2011 | 8/31/2011 | 8/31/2011 | P | DONE |
Troy Cobbley
|
|
|
Performed site visit to determine placement of heat detectors and found that the city approved plans do not show the heat detectors spaced for "sloped" ceilings, "High" ceilings or spacing taking "beam construction" into account. The plans also do not reflect the existing fire sprinkler riser which includes two interior tamper switches, an exterior wall PIV and a flow switch. After a discussion with plan review it was determined that a plan modification/resubmittal is needed to show this information. This was relayed to the fire alarm tech.
|