Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberFIR11-00431
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer NumberC15044
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing protection in the System 2 Mechanical areas. There is upright sprinkler protection in a large mechanical area and loading dock. There is pendent sprinkler in a Temp Lab area, and several corridors. A large long chase is designated as non-combustible.

Note: The fire protection in the subfloor area below the AMHS Clean Link was not submitted and has not been reviewed at this time.

Note: See permit FIR11-00301, FIR11-00365 for the review on other portions of this building


Building Department Scope:

Micron Building B50 - R&D Building - To construct a new 111,005 square foot, two story, with 71,855 square foot basement, concrete and steel semiconductor fabrication R & D facility and related site improvements. The first floor level is 89, 435 sq. ft. (60,100 sq. ft. finished and 29,325 sq. ft. unfinished). The second floor is a 21,570 sq. ft. mechanical space (16,170 sq. ft. used and 5,400 square feet future). The basement level (subfab.) has 43,295 sq. ft. finished and 28,560 unfinished. All construction per the approved plans and attached comment list.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/3/201212/3/201212/3/2012PPASS
DetailsForrest France
Permit finaled.
INSP-Final Inspection11/30/201211/30/201211/30/2012PCANC
DetailsTroy Cobbley
Per james and I's discussion this inspection will be rescheduled for monday. Phone #: ###-####
INSP-Final Inspection11/19/201211/19/201211/19/2012PPART
DetailsForrest France
All modifications to the original design to be shown on as-built drawings including additional heads under ductwork at the dock area. Remainder of revisions are acceptable.
INSP-Final Inspection10/25/201210/25/201210/30/2012PPEND
DetailsForrest France
Final pending record drawings to match installation and final walkthrough.
INSP-Final Inspection10/22/201210/22/201210/30/2012PPART
DetailsForrest France
Provide as-built drawings to match field installation including added heads for obstructions and modifications to pipe routing.
INSP-Final Inspection10/17/201210/19/201210/30/2012APART
DetailsForrest France
Re-inspection of previous C/N items.
INSP-Sprinkler Rough-in4/10/20124/11/20124/12/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in4/2/20124/3/20124/4/2012PPART
DetailsForrest France
Inspection items listed 3/30 remain unchanged with the exception of one retainer at the dock and field ceiling tile in place where grid is complete at the non-clean link. Ceilings and sprinkler protection are still lacking at vestibule 100P, closet @ RR 100F, room 100J, column line K, link intersection, and GR100H.
INSP-Sprinkler Rough-in/Hydro3/30/20124/2/20124/2/2012PPART
DetailsForrest France
Overhead hydrostatic test passed.
INSP-Sprinkler Rough-in/Hydro3/29/20123/30/20123/30/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro3/28/20123/29/20123/30/2012AFAIL
DetailsForrest France
Overhead hydrostatic test failed due to visible leakage on the system and pressure loss at the gauge. Re-inspection items noted include; lacking coverage at vestibule 100P- temporary bootie room (missing ceiling and sprinkler heads, outlets are plugged), SW stair 100W exit landing is partially sprinklered, missing field ceiling tile at the TEM labs, leak at non-clean link 100A, construction at the closet adjacent to RR 100F is incomplete, NW stair landing is partially sprinklered, missing ceiling and sprinkler coverage at non-clean link room 100T, missing ceiling tile at non-clean link, heads not installed at column line K temporary wall NE exit, missing head and ceiling at link intersections, secure retainer at dock corridor, noted 5 added uprights not shown on plans below dock area ductwork, plugged outlet and missing ceiling at GR 100H.
INSP-Sprinkler Rough-in/Hydro3/27/20123/28/20123/28/2012ANR
DetailsForrest France
Need hydrostatic test. Plan modification required for field changes to the approved design including added heads in the calc. area- ref. activity notes dated 2/22/12.
INSP-Sprinkler Rough-in/Hydro3/2/20123/2/20123/2/2012PNR
DetailsForrest France
Deluge valve installation incomplete at this time. Main and branchline including drops in place. Two drops in need of adjustment.
INSP-Sprinkler Rough-in/Hydro2/28/20122/29/20123/1/2012APART
DetailsForrest France
Re-inspection for system 2 corrections finished at the following locations: hall 100R including added seismic bracing, hangers, and spacing okayed with the exception of one area at the intersection of the corridors @ 140ft2: west stair 100W okay for cover: TEM labs 104B thru 104D approved for cover, noted cap at 4" grid main in TEM lab 104E terminates inside a sheetrock wall: auxillary drain at the 4" main relocated to the 6" main at link 100A.
INSP-Sprinkler Rough-in/Hydro2/20/20122/21/20122/22/2012PPART
DetailsForrest France
Reinspection items at system 2 mechanical include added heads at several locations-6 areas, approx 14 ssu- some in the calc area, rough-in at link 100A okayed, ft2 at corridor 100R not to exceed 130 after pendents are cut in, corrections at nonclean link and TEM labs are incomplete, dock 100C and vestibule 100D no change.
INSP-Sprinkler Rough-in1/23/20121/24/20121/25/2012PFAIL
DetailsForrest France
Initial rough-in inspection for system # 2 completed and failed due to several issues. General description of such items include and are not limited to; system mains and branch lines at some areas are not installed to design dimentions off walls and columns, 4" main and fittings halfway inside a sheetrock wall, missing crosses for pendent arm-overs at the TEM lab branch pipe, missing coverage below ductwork and other obstructions over 4' throughout the mechanical rooms, incomplete seismic bracing, overspaced coverage at the corridor, added heads at the stair and a new room not reflected on plans, additional storage room adjacent to the loading dock without protection, no access to view installation above the new bootie room, open outlet and missing heads at the end and beginning of the 2 1/2' dirty link branch line- also need to install and secure retainers, etc.