Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberFIR11-00448
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameB50-R&D EXPANSION BLD
Customer NumberC15044
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing protection for the SubFab System 10 Mechanical. The system is a 4”x3”x2” grid.

Note: See related permits FIR11-00301, FIR11-00365, FIR11-00431

Plan Mod #1
Revised due to as built changes and design omissions. Removed (21) sprinklers from inside a duct near column T and between 17-4 as shown on drawing FP8. If the duct is conveying gases, vapors, fumes, mists or dust sprinklers ARE required inside the duct. If the duct is combustible nonmetallic sprinklers ARE required. . IFC: 1803.10.4
Field Inspector, please verify the duct above.

Plan Mod #1 Rev 1 7/13/2012, 7/18/2012, 7/30/2012
Revised due to as built changes. Added, new 3” express main
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/19/201212/19/201212/19/2012APASS
DetailsForrest France
INSP-Final Inspection10/22/201210/22/201210/30/2012PPART
DetailsForrest France
Verified plan modifications, completed final walkthrough. Pending heads at fiberglass FE duct.
INSP-Final Inspection10/17/201210/18/201210/19/2012PNR
DetailsForrest France
INSP-Sprinkler Rough-in/Hydro10/17/201210/18/201210/19/2012APART
DetailsForrest France
Completed hydrostatic testing of the new 3" main.
INSP-Sprinkler Rough-in4/4/20124/4/20124/4/2012PPART
DetailsForrest France
Previous correction items including retainers and seismic bracing at mech. room 44, and overspaced coverage at N. mech. access finished. Plan modification pending.
INSP-Sprinkler Rough-in/Hydro3/30/20123/30/20123/30/2012APART
DetailsForrest France
Hydrostatic re-test of system 10 passed 3/29 PM.
INSP-Sprinkler Rough-in/Hydro3/28/20123/29/20123/30/2012AFAIL
DetailsForrest France
Overhead hydrostatic test failed due to pressure loss at the gauge. Noted re-inspection items include; plan resubmittal required due to: 18 additional upright heads not shown on the original design or included in the calculations, added 45's and 90's at the 4" grid mains, 2 1/2" main has been changed to 3", column protection is not included, missing longitudinal brace at mech. room 44, secure two retainers, upright coverage at the north mechanical access area is overspaced at 140ft2. Previous corrections finished are; sprig height at beams, axis adjustment, spacing at mechanical access 47 and south mech. access.
INSP-Sprinkler Rough-in/Hydro3/6/20123/7/20123/7/2012APART
DetailsForrest France
Inspection for cover at the new drop ceiling in the SW stair completed.
INSP-Sprinkler Rough-in/Hydro2/28/20123/1/20123/2/2012ANR
DetailsForrest France
>> Inspection requested via web by Alicia Pauley *Contractor unable to locate plan set*
INSP-Sprinkler Rough-in/Hydro2/28/20122/29/20122/28/2012ACANC
DetailsForrest France
Phone #: ###-#### >> Inspection requested via web by Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro2/20/20122/22/20122/23/2012AFAIL
DetailsForrest France
Refer to activity notes 2/23.
INSP-Sprinkler Rough-in/Hydro2/22/20122/23/20122/23/2012AFAIL
DetailsForrest France
System 10 inspection failed due to multiple deficiencies including; mechanical room 44- overspaced coverage at the west wall, five uprights below max. distance from the deck, missing seismic brace at 4" main, 3" main has been installed in place of 2 1/2" per the approved plan, 4" main installed on the opposite side of the beam, 6" feed main has been relocated, four 45 deg. ells have been added to the 4" main. Missing retainer at NW stair 60, four added 45 ells at S/W stair main. Mechanical access area- 4 upright heads exceed min. separation distances, added 90's at branchline, missing retainers, overspaced upright adjacent to division wall. Mechanical mezzanine 43- blocked heads at new beams, 10 added 90's at one 2" branchline, several sprig-ups are out of axis, noted approx. 15 added heads under various obstructions which are not included in the design. Access unavailable at one portion of the mechanical service area. Due to project schedule and a majority of plant process equipment already installed, some aspects of the system are not accessible for satisfactory inspection.