INSP-Final Inspection | 2/15/2012 | 2/16/2012 | 2/16/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/15/2012 | 2/15/2012 | 2/15/2012 | P | FAIL |
Troy Cobbley
|
|
|
Still need the zone map as discussed and signage on the bell and riser room door. Inspection rescheduled for tomorrow morning per conversation with CM company.
|
INSP-Sprinkler Rough-in | 2/13/2012 | 2/14/2012 | 2/14/2012 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in Corridor 222 can be covered. As-builts are approved. To final the project a sticker is needed for the outside alarm bell, forward flush of the backflow, sprinkler work finished at the main entry/foirer and testing of the flow switches. Also a sprinkler system coverage/zone map is needed at the risers for fire dept use.
|
INSP-Final Inspection | 2/10/2012 | 2/13/2012 | 2/13/2012 | P | CANC |
Troy Cobbley
|
|
|
Can not final until previous corrections on wrong size piping and routing in remote area has been addressed.
|
INSP-Sprinkler Rough-in | 2/10/2012 | 2/13/2012 | 2/13/2012 | A | FAIL |
Troy Cobbley
|
|
|
The pipe size installed in Corridor 222 does not match the approved plans. Also per the fitter some pipe routing changes were needed in the remote area. Piping can not be covered.
|
INSP-Sprinkler Rough-in | 2/10/2012 | 2/10/2012 | 2/10/2012 | P | FAIL |
Troy Cobbley
|
|
|
The sprinkler fitter was not ready for an inspection. He will reschedule for monday.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2012 | 1/24/2012 | 1/24/2012 | P | PASS |
Troy Cobbley
|
|
|
The hydro test at the riser passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2012 | 1/24/2012 | 1/24/2012 | A | PART |
Troy Cobbley
|
|
|
The hydro test for the system at the new lobby passed. The hydro test for the system at the new riser failed possibly due to the door to the riser room being left open. This test is rescheduled for this afternoon.
|
INSP-Sprinkler Rough-in | 1/20/2012 | 1/23/2012 | 1/23/2012 | P | PASS |
Troy Cobbley
|
|
|
All of the sprinkler piping in the new addition area located above the lay-in ceiling tile can be covered. The remodeled areas have not been inspected yet.
|
INSP-Conference | 1/19/2012 | 1/20/2012 | 1/20/2012 | P | DONE |
Troy Cobbley
|
|
|
Mike and I discussed not installing the two pendant heads in the soffit surrounding the sky light in the main entry/lobby. It is less than 4' at all points and typically only 18" wide. The sky light is covered by a sidewall sprinkler head. I'm ok with deleting the two soffit pendants. We also discussed scheduling cover inspections for the remaining areas
|
INSP-Sprinkler Rough-in | 12/14/2011 | 12/14/2011 | 12/16/2011 | P | PASS |
Troy Cobbley
|
|
|
The west side mens and womens restrooms are ok to cover
|
INSP-Sprinkler Rough-in | 12/2/2011 | 12/5/2011 | 12/5/2011 | A | PASS |
Troy Cobbley
|
|
|
The city approved drawings were found and I compared them to the as-builts. They seem to match except that the two remote areas, Main Lobby and Banquette Room, are not shown on the as-builts.
|
INSP-Sprinkler Rough-in | 12/1/2011 | 12/2/2011 | 12/2/2011 | A | PART |
Troy Cobbley
|
|
|
The overhead piping in the new addition area is complete except for the drops and the Main Entry area. These two items will need to be inspected when completed prior to a cover being given to cover the piping with the lay-in ceiling tile. The sprinkler piping above the hard lid areas of the new addition is ok for cover. The installation so far matches the provided as-builts. The city approved plans were not available and will need to be provided prior to any more inspections.
|
INSP-Sprinkler Rough-in | 11/28/2011 | 11/29/2011 | 11/28/2011 | A | CANC |
Troy Cobbley
|
|
|
Please call 1/2 hr prior to inspection. Leroy is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 11/23/2011 | 11/28/2011 | 11/28/2011 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. The general contractor and I noted overspaced upright coverage along the east wall and in the riser room.
|
INSP-Conference | 11/4/2011 | 11/7/2011 | 11/7/2011 | A | DONE |
Troy Cobbley
|
|
|
Mike and I went over upright sprinkler spacing to the truss obstructions.
|