Permit Information
Permit NumberFIR11-00483
StatusFinaled
Name JBL FIRE PROTECTION LLC
Site Address 3676 E WARM SPRINGS AVE
Project Name3051 WISE WAY
Customer Number 
ePlanReviewNo
Description
The Fire Sprinkler Scope of work consists of providing above and below fire protection in a new two level firehouse. Each level is protected with a tree system utilizing telescoping branch piping. There is a small antifreeze system in the Attic Crown. The system is supplied through 6” underground with a 4” reduced pressure backflow preventer to floor control valves. The system has been designed for light hazard throughout except for the apparatus bay, which is ordinary hazard group I.


Building Department Scope:

Boise Fire Station #15 - To construct a new 11,210 square foot, two story, wood framed and masonry fire station and related site improvements. This building is fully fire sprinkled. First Floor: 8,210 sq. ft. Second Floor: 3,000 sq. ft.. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/5/20127/5/20127/6/2012PPASS
DetailsForrest France
Final walkthrough and inspection completed satisfactory. Fire sprinkler permit finaled.
INSP-Final Inspection6/22/20126/22/20126/22/2012PNR
DetailsForrest France
Final pending project related fire alarm permit work.
INSP-Final Inspection6/19/20126/21/20126/21/2012APART
DetailsForrest France
For inspection items noted 6/18.
INSP-Final Inspection6/18/20126/18/20126/18/2012PCANC
DetailsTroy Cobbley
Jeremy actually wanted a conference/walk through. I found one upright sprinkler head in a second floor room that is blocked by a surface mounted light. Also several pendant heads in the truck bay have ordinary temp heads in locations where intermediate and high temp. heads are required at the unit heaters.
INSP-Sprinkler Rough-in/Hydro4/16/20124/16/20124/19/2012PPART
DetailsForrest France
Pendent head relocations at sheetrock ceilings due to fixture obstructions.
INSP-Sprinkler Rough-in/Hydro4/12/20124/13/20124/13/2012APASS
DetailsTim Frost
Both systems passed overhead hydro.
INSP-Sprinkler Rough-in/Hydro3/5/20123/5/20123/5/2012APASS
DetailsForrest France
Rough-in passed.
INSP-Sprinkler Rough-in1/19/20121/19/20121/24/2012PPART
DetailsForrest France
INSP-Sprinkler Rough-in1/23/20121/23/20121/23/2012APART
DetailsForrest France
Noted correction items finished. Overhead rough-in only passed.
INSP-Sprinkler Rough-in1/17/20121/18/20121/18/2012PPART
DetailsForrest France
Rough-in inspection completed. Noted items include obstructed upright coverage at the 1st and 2nd floors at some locations due to ductwork, adjacent truss webs, etc. Verified previous c/n items.
INSP-Sprinkler Rough-in1/17/20121/17/20121/18/2012PPART
DetailsForrest France
C/N items include missing coverage below stairway at the concealed space, obstructed pendent heads at two restrooms, need to provide coverage at combustible concealed spaces or meet allowable exceptions per NFPA 13, plans do not show pendent heads at the equipment bay area.
INSP-Conference1/17/20121/17/20121/17/2012ADONE
DetailsForrest France
Regarding location of the wall post indicator control valve.
INSP-Supply line flush10/6/201110/7/201110/7/2011PPART
DetailsForrest France
UG fire supply line flush completed acceptable.
INSP-Sprinkler Rough-in/Hydro9/30/20119/30/20119/30/2011PPASS
DetailsForrest France
UG fire supply line hydrostatic testing passed.
INSP-Sprinkler Rough-in9/27/20119/27/20119/28/2011PPASS
DetailsTroy Cobbley
Underground cover inspection passed. Piping can be covered.