INSP-Final Inspection | 5/7/2012 | 5/8/2012 | 5/8/2012 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/30/2012 | 4/4/2012 | 4/4/2012 | P | CANC |
Troy Cobbley
|
|
|
To be cancelled per Stefan Phone #: ###-####
|
INSP-Final Inspection | 2/21/2012 | 2/29/2012 | 2/29/2012 | P | CANC |
Troy Cobbley
|
|
|
Stephan Hauge ###-####
|
INSP-Supply line flush | 2/3/2012 | 2/6/2012 | 2/6/2012 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed. On walking through the project I noted alot of painted sprinkler pendants that will require replacement.
|
INSP-Sprinkler Rough-in | 12/1/2011 | 12/1/2011 | 12/1/2011 | P | PASS |
Troy Cobbley
|
|
|
The tenting is complete except for the top of the riser to main feed. This will be verified later. Piping can be covered.
|
INSP-Sprinkler Rough-in | 11/15/2011 | 11/16/2011 | 11/16/2011 | A | PASS |
Troy Cobbley
|
|
|
The underground supplt piping is ok to bury
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. One pendant needs to be relocated in the Laundry room and as-builts showing the revised pipe routing are needed. The tenting still needs to be done.
|
INSP-Sprinkler Rough-in | 11/11/2011 | 11/14/2011 | 11/14/2011 | P | FAIL |
Troy Cobbley
|
|
|
The original copies of the city approved plans were not on site so no rough-in inspection was performed. Also the installation was not complete. I went over underground supply requirements with the driller and Jim the owner.
|