INSP-Final Inspection | 2/27/2012 | 3/1/2012 | 3/2/2012 | P | PASS |
Forrest France
|
|
|
Remainder of correction items verified for completion. Fire alarm permit finaled.
|
INSP-Final Inspection | 2/17/2012 | 2/22/2012 | 2/22/2012 | P | PART |
Forrest France
|
|
|
Completed satisfactory testing for the elevator control functions including machine room, hoistway and lobby SD and HD, shunt and control voltage monitor.
|
INSP-Final Inspection | 2/14/2012 | 2/17/2012 | 2/17/2012 | P | PART |
Forrest France
|
|
|
Completed testing for fire sprinkler monitoring including all floor control manifolds and pump room devices. Items noted include one non-functional TS at the 4th floor and two pump bypass tampers to be replaced.
|
INSP-Final Inspection | 2/9/2012 | 2/13/2012 | 2/14/2012 | P | PART |
Forrest France
|
|
|
Completed notification appliance testing 1st thru 7th floors, verified previous C/N items. Decibel levels at the 1st floor common restrooms exceed max. allowable- provide strobe only per plan at these locations. Verified visual coverage at all ADA rooms, provide WP appliances where noted.
|
INSP-Alarm Testing | 2/9/2012 | 2/9/2012 | 2/10/2012 | P | PART |
Forrest France
|
|
|
Completed testing of room heat detection devices throughout the 1st to 7th floors including system SD at ADA rooms. Noted items include 4 HD to be replaced, sync issues on the 7th floor, insufficient cd settings at ADA room notification appliances, four units in which access was denied for inspection purposes.
|
INSP-Final Inspection | 2/3/2012 | 2/6/2012 | 2/8/2012 | A | PART |
Forrest France
|
|
|
Verified previous correction items. Some issues remain including coverage at the 2nd floor operations office, raceway at the 4th floor, old system lobby SD's still in place, lock at FACP breaker. Alarm, trouble and supervisory signals were tested- however the zone 4 (supervisory) signals were undefined at central station monitoring. Discussed items remaining, inspection schedule, etc.
|
INSP-Alarm Testing | 1/24/2012 | 1/24/2012 | 1/24/2012 | A | PART |
Forrest France
|
|
|
|
INSP-Final Inspection | 1/18/2012 | 1/20/2012 | 1/24/2012 | P | PART |
Forrest France
|
|
|
Completed initial walkthrough. Noted items in need of adjustment, incompleted items such as the remote annunciator, record of inspection and testing forms, removal of old system horns, detectors, MP's. Discussed inspection schedule.
|
INSP-Final Inspection | 1/4/2012 | 1/5/2012 | 1/5/2012 | A | NR |
Forrest France
|
|
|
Robert Phone #: ###-####
|